Date: xxx
Ref. xxx
To:
M/s. xxx Consulting Architects and Engineers
Dubai, UAE
Kind Attn: Mr. xxx
Project: 2B + G + 14+ Lower Roof Hotels Building on Plot No. xxx at Barsha, Dubai.
Subject: Surface preparation of water proofing
Dear Sir,
As per site visit on today evening Mr.xxx said that the surface is not ready to receive primer at water tank area at basement –II level.
Here as a contractor this area is our responsibility to precede the work which is holding since two days, so the project progress is not suffer as show far.
Regards,
For xxx Contracting L.L.C
xxx
Project Manager