Response to Factory visit at xxx for B11- Corporate Housing Pods.

Site Meeting
Site Meeting

Our Ref: xxx

Date: xxx

To                    :           xxx Construct Company Ltd.

                                    P. O. Box xxx

            Abu Dhabi – UAE.

Attention          :           Eng. xxx

                        :           Project Director

Subject            :           Response to Factory visit at xxx for B11- Corporate Housing Pods.

Dear Mr. Yasser,

In reference to the factory visit report dated xxx, please find attached our response and compliance along with the approved inspection request particularly for the point no.05.

We trust this is acceptable and considered that, this is closed.

This is for your information and record.

On behalf of xxx LLC

xxx

Projects Manager                 

By Md Abu Zaed Khan