Request to client to pay directly to the supplier for long lead item

advance payment
advance payment

Date:               xxx

Ref:                  xxx

Kind Attn         :Mr. xxx

Project:            2B + G + 14+ Lower Roof Hotel Building on Plot No. xxx at Al Barsha 1st, Dubai

Subject             :  Request to client to pay directly to the supplier for long lead item or major procurement items.

Dear Sir,

With regards to the subject above, as we discussed with the client to help us financially to release the payment for the major item to procure at this stage which help the contractor early delivery.

We are attaching the supplier quotation herewith and find the details below:

Sl No.Description of the item to be procuredName of the supplier and quotation referenceAmount (AED)
1LV SwitchgearSAFETY ELECTRICAL  GROUP Proforma Invoice No: SESM/PI/17/1018 date 11.04.17 P.O No: 1700152728,000.00
2Firefighting pump setBahri & Mazroei Technical Syatem Co. LLC Proforma Invoice No. PI/FFS/SH/17-24-A date 12.04.17241,709.40
3Electric Busbar DuctTransbar Middle East LLC Proforma Invoice No. 1700078  date 11.02.17275,000.00
4GRP Water TanksFikree Pipe LLC Proforma Invoice No. PF0080/17  date 13.04.17133,600.00
TOTAL AMOUNT (AE Dirhams):1,378,309.40

In word AE Dirhams: 1,378,309.00 (AE Dirhams: One million three hundred seventy eight thousand three hundred nine and forty Fils only)

So, kindly do the needful and awaited for your early reply.

Regards,

For xxx Contracting L.L.C.

xxx

Project Manager

By Md Abu Zaed Khan

Hello, this is Engr. Zaed Khan Planning Engineer, Associate member of Society of Engineers UAE. Expert in construction project planning, FIDIC red book, computation of extension of time claim, Contract agreement and contractual letters.

Leave a comment

Your email address will not be published. Required fields are marked *

Exit mobile version