Variation notification

Reminder of letter communication to xxx

Date:               xxx

Ref:                  xxx

Kind Attn         :Mr. xxx

Project:            2B + G + 14+ Lower Roof Hotel Building on Plot No. xxx at Al Barsha 1st, Dubai

Subject         : Reminder of letter communication to Danway with reference CC/DANWAY/05

          dtd. 21.05.17

Dear Sir,

With reference to the above, we would like to intimate that no actions taken from our letter

communication to the nominated cradle subcontractor till date.

So,  we would like to request you to intimate the employer that subcontractor must update and submit the drawing otherwise any issue if arise for the coordination with aluminum subcontractor it will be serious to resolve as well as we are also plastering without knowing the requirement of the cradle with the structure

This is your kind information and do needful and we client to interfere and to avoid the risk/miscoordination

Regards,

For xxx Contracting L.L.C.

xxx

Project Manager