Date : xxx
Ref : CC/DESTEC/011
To : M/s. xxx GROUP, PO Box 47395, Sharjah UAE.
Project : 2B + G + 14 + Lower Roof Hotels Building on Plot No. 373-1297 at Barsha, Dubai.
Subject : Regarding your Letter Ref. NO. DES/CM/AP/CC/05 dated 18/10/17 and Ref. No. DECS/CM/AP/CC07 dated 06/11/17
Dear Mr. xxx,
With reference to the above mentioned subject, please find our reply and concerns as below:
- Refer with Letter. Ref. No. DECS/CM/AP/CC07 dated 06/11/17, our clearance in order of your item dated as below:
- DES – Provide us the schedule of All Day Dining above ceiling MEP work completion to start our ceiling frame work (DES/CM/AP/RIW/003/R01) dated 01st Nov. 2017 / column issues from awaited from the consultant.
CC – MEP works in HR will be completed by 16/11/2017
- DES – Provide us the schedule of All Day Dining wall MEP work completion to start our wall paint preparation work for receive paint (DES/CM/AP/CC/ADD/RIW/005) dated 01st November 2017.
CC – Will be completed by 16/11/2017
- DES – Please check MEP work for completion in All Day Dining to start floor screeding work (DES/CM/AP/CC/ADD/RIW/002/R01) dated 01st November 2017.
CC –will start on 19/11/2017
- DES – Please check MEP work completion in Stag Bar as we already start our ceiling frame work (DES/CM/AP/CC/SD/RIW/003/R01) dated 01st November 2017.
CC – co-ordination in progress
- DES – Provide us the schedule of Stag Bar wall MEP work completion to start our wall paint preparation work for receive paint (DES/CM/AP/CC/SB/RIW/006) dated 1st November 2017.
CC – we advise to finish screed works first and proceed the paint after. By that time we will clear all our issues.
- DES – Please check MEP work completion in Stag Bar to start floor screeding work (DES/CM/AP/CC/SB/RIW/002/R01) dated 01st November 2017
CC – 13/11/2017
- Your statement that your team is idle due to non-availability of work clearance, we are not accepting this statement since we have only MEP works, and MEP drawings was issued recently as you did not provide the approved drawings.
- The co-ordination between Emirates Kitchen, your company being carried out directly and finally we resolve the same so it is you who is lacking co-ordination.
This is for your kind information and records.
Regards,
xxx
Project Manager