Regarding the receiving delivery of the lights and washbasin

Regarding the receiving delivery of the lights and washbasin

Date: xxx

Ref: CC/269/CM/47

To                          : M/s. xxx, Dubai, UAE

Kind Attn              : Mr. xxx

Project            : 2B + G + 14+ Lower Roof Hotel Building on Plot No. 373-1297 at Al        Barsha 1st, Dubai U.A.E.

Subject                 Regarding the receiving delivery of the lights and washbasin

Dear Sir,

With reference of the above mentioned subject, we would like to inform you that we have severe space issue at the site to storage of the washbasin and lights.

So, we are requesting to be stored with you and we will collect as per progress of the work.

Kindly support us and request to do the needful.

Thanking you,

For xxx Contracting L.L.C

xxx

Project Manager

Leave a Reply

Your email address will not be published. Required fields are marked *

× How can I help you?
Seraphinite AcceleratorOptimized by Seraphinite Accelerator
Turns on site high speed to be attractive for people and search engines.