PT drawing for 14th floor and roof and upper roof that issued

Shop Drawing

Shop Drawing

Date:               xxx

Ref:                  xxx

Kind Attn         :Mr. xxx

Project:            2B + G + 14+ Lower Roof Hotel Building on Plot No. xxx at Al Barsha 1st, Dubai

Subject         : Regarding PT drawing for 14th floor and roof and upper roof that issued by DM with Bldg Permit  xxx

Dear Sir,

With reference to the above, we would like to acknowledge that the revised PT drawing received from your office, kindly note the following:

  1. We are starting the work at 14th floor slab level as per new drawing which was under hold due

to drawing from long time.

(before issuing of execution certification.

So, kindly review the notes  from building permit and note no. one” must be complied before slab casting related DCD drawing to be address before the slab.

Meantime, other impact scope, cost and schedule will be analyze.

Regards,

For xxx Contracting L.L.C.

xxx

Project Manager