Demobilization of Tower Crane TC-01 & TC-02 at Blocks A & B

Tower Crane

Our Ref: xxx Date: To xxx Contracting LLC P. O. Box xxx Dubai, U.A.E. Attention            : Mr. xxx, Group Procurement Manager Project                 : xxx Phase 2 Subject                 : Demobilization of Tower Crane TC-01 & TC-02 at Blocks A & B Dear Sir, We acknowledge the receipt of your letters xxx dated 31 January xxx &… Continue reading Demobilization of Tower Crane TC-01 & TC-02 at Blocks A & B

Pods Vanity Counter top & Cistern Top deviation against approved top material

Marble Vanity Top

Our Ref: xxx Date: To xxx Contracting LLC P. O. Box xxx Dubai, U.A.E. Attention            : Mr. xxx, Group Procurement Manager Project                 : xxx Phase 2 Subject                 : Pods Vanity Counter top & Cistern Top deviation against approved top material References         : Dear Sir, We refer to your letter ref: xxx dated 23 January xxxx… Continue reading Pods Vanity Counter top & Cistern Top deviation against approved top material

Response to allegations of delay in Delivery of PODs, MIR & WIR Approvals

Approval and Finalization

Our Ref: xxx Date: To xxx Contracting LLC P. O. Box xxx Dubai, U.A.E. Attention            : Mr. xxx, Group Procurement Manager Project                 : xxx Phase 2 Subject                 : Response to allegations of delay in Delivery of PODs, MIR & WIR Approvals References         : Dear Sir, We refer to your letter ref: xxx dated 31 January… Continue reading Response to allegations of delay in Delivery of PODs, MIR & WIR Approvals

Notice of Delay in Delivery of PODs

Pods Delivery

Our Ref: xxx Date: To xxx Contracting LLC P. O. Box xxx Dubai, U.A.E. Attention            : Mr. xxx, Group Procurement Manager Project                 : xxx Phase 2 Subject                 : Notice of Delay in Delivery of PODs Dear Sir, We refer to your letter ref: xxx dated 12 January xxxx and respond as follows: In reply to… Continue reading Notice of Delay in Delivery of PODs

Notice of Delay in Delivery of PODs, MIR & WIR Approvals

Approval

Our Ref: xxx Date: To xxx Contracting LLC P. O. Box xxx Dubai, U.A.E. Attention            : Mr. xxx, Group Procurement Manager Project                 : xxx Phase 2 Subject                 : Notice of Delay in Delivery of PODs, MIR & WIR Approvals References         : Dear Sir, We refer to your letter ref: xxx dated 12 January xxxx and… Continue reading Notice of Delay in Delivery of PODs, MIR & WIR Approvals

Reply to allegations of delay in submission/approval of WIRs

Response to Delay in Delivery of PODs

Our Ref: xxx Date: To xxx Contracting LLC P. O. Box xxx Dubai, U.A.E. Attention            : Mr. xxx, Group Procurement Manager Project                 : xxx Phase 2 Subject                 : Reply to allegations of delay in submission/approval of WIRs References         : Dear Sir, We refer to your letter ref: xxx dated 12 January xxxx and respond as… Continue reading Reply to allegations of delay in submission/approval of WIRs

POD’s marble color deviations against approved marble top material

Marble Vanity Top

Our Ref: xxx Date: To xxx Contracting LLC P. O. Box xxx Dubai, U.A.E. Attention            : Mr. xxx, Group Procurement Manager Project                 : xxx Phase 2 Subject                 : POD’s marble color deviations against approved marble top material Dear Sir, We are writing in response to your letter ref: xxx dated 26th December and with reference… Continue reading POD’s marble color deviations against approved marble top material

Undertaking Letter concerning the functionality of water pipes and electrical conduits

METHOD STATEMENT WATER SUPPLY WORK

Our Ref: xxx Date: To xxx Contracting LLC P. O. Box xxx Dubai, U.A.E. Attention            : Mr. xxx, Group Procurement Manager Project                 : xxx Phase 2 Subject                 : Undertaking Letter concerning the functionality of water pipes and electrical conduits Dear Sir, We are writing with regards to the crossing of the water pipes and the… Continue reading Undertaking Letter concerning the functionality of water pipes and electrical conduits

Discrepancies in Payment Certificate No.1 issued on 28th December xxxx

Delay in the certification of our invoice

Our Ref: xxx Date: To xxx Contracting LLC P. O. Box xxx Dubai, U.A.E. Attention            : Mr. xxx, Group Procurement Manager Project                 : xxx Phase 2 Subject                 : Discrepancies in Payment Certificate No.1 issued on 28th December xxxx Dear Sir, With reference to the subject mentioned above, we acknowledge the receipt of the Payment Certificate… Continue reading Discrepancies in Payment Certificate No.1 issued on 28th December xxxx

Delivery of Pods without Marble Top

Pod Delivery Schedule

Our Ref: xxx Date: To xxx Contracting LLC P. O. Box xxx Dubai, U.A.E. Attention            : Mr. xxx, Group Procurement Manager Project                 : xxx Phase 2 Subject                 : Delivery of Pods without Marble Top References         : M/s xxx (Contractor Name) letter ref xxx dated 26-Nov-xxx                                BGC Letter ref xxx dated 27-Dec-xxx Dear Sir, We… Continue reading Delivery of Pods without Marble Top