Project:            2B + G + 14+ Lower Roof Hotel Building on Plot No. xxx at Al Barsha 1st, Dubai

Subject      : Regarding nomination of the UPS supplier and finalization of the UPS room for coordination with low voltage sub contractors.

Dear Sir,

With reference to above we would like to inform you that the xxx Emirates required the UPS supplier nomination and the UPS configuration for the required connectivity and the location for UPS to be finalize immediately.

So the xxx Emirates have serious concern now for nomination of the UPS supplier and location of the room as well as the parameter of the connectivity with UPS.

This is for your kind information and to do needful as soon as possible.

Regards,

For xxx Contracting L.L.C.

xxx

Project Manager

By Md Abu Zaed Khan

Hello, this is Engr. Zaed Khan Planning Engineer, Associate member of Society of Engineers UAE. Expert in construction project planning, FIDIC red book, computation of extension of time claim, Contract agreement and contractual letters.

Leave a comment

Your email address will not be published. Required fields are marked *

Exit mobile version