Date: xxx
Ref.: xxx
Total Pages: 1
To,
xxx
Attention: xxx
Project: xxx.
Subject: Delay in Nomination of Provisional Sum & Prime Cost Subcontractors
Reference: MCM/AAZ/OCAC/04/2019 dated 26th November 2019
MCM/AAZ/OCAC/05/2019 Reminder -1 dated 8th December 2019
MCM/AAZ/OCAC/05/2019 dated 24th December 2019
MCM/AAZ/OCAC/07/2019 dated 6th January 2020
Dear Sir,
With reference to above cited letters, we wish to put on record there has been a significant delay in nomination of provisional items and selection of Prime Cost Items. The delay in nomination and selection will affect the project critical path and delay the overall project completion. Following are the Provisional Sum items to be nominated by Client and Prime Cost Items list are attached.
Sl. No. | BOQ Ref. | Item Particular | Impacted Activities | Remarks |
1 | BOQ REF. 3/50/G | Swimming Pool Works | Approval of Shop Drawing, Materials. Submission of LV Load schedule to DEWA. | |
2 | BOQ REF. 4/52/A | HVAC Air Conditioning Works | Builders Works, Approval of HVAC Shop Drawing, Materials, RCP and MEP Coordination Shop Drawing. Submission of LV Load schedule to DEWA. | |
3 | BOQ REF. 5/8 | Light Fighting Supplier | Submission of LV Load schedule to DEWA. | |
4 | BOQ REF. 5/9 | Switch and Socket Supplier |
Upon receipt of subcontractor/supplier nomination MCM will enter a subcontracting agreement/ issue LPO, the next step will be securing Engineer approval for shop drawing and materials. Once required approval are secured then only materials delivery lead time will be started. Depend upon selection of materials the lead time may vary 4 weeks to 14 weeks. Considering said scenario Provisional Sum and Prime cost subcontractor/supplier nomination are extreme critical at current stage to complete the project as agreed completion time.
The Contractor reserve its right pursuant to Sub-Clause 6.3, 44.1(d) and 53.1 of Condition of contract to claim time and cost implication due to delay in nomination of provisional sum and prime cost subcontractor/supplier.
Therefore, we request your urgent intervention to address this matter by asking to the Client to finalize the pending nominations on top priority basis.
Thank You
Yours Sincerely
XXX