Method Statement Title: Testing & Commissioning of Fire Protection System

3-tips-for-Fire-Pump

3-tips-for-Fire-Pump

Method Statement Title: Testing & Commissioning of Fire Protection System

Scope :

This scope of this method statement covers the testing and commissioning of sprinklers and Wet Riser system within the Burj Dubai – The Residences in accordance with the following.

  1. Technical specifications 15500.
  1. NFPA-13 &  NFPA-14.

Note: Method statement for the startup and commissioning of fire pump set will be covered under a separate submittal (Ref. P-015)

2.0     Purpose :

To test the sprinklers and Wet Riser system for leaks and defects and to perform all required acceptance tests in accordance with NFPA-13 & NFPA-14 (Inspection and testing of water based Fire Protection Systems).

3.0     Applicable locations:

4.0     Parties Involved :

            M/s. Emaar Properties            :           Client

            M/s. Mace                               :           Project Manager

            M/s.Roberts & Partners          :           MEP Consultant

            M/s. ETA                                :           MEP Sub-Contractor

            M/s.NMX                               :           Main Contractor

M/s.FIREX                             :           Fire Protection Contractor

Pressure Guage – 4” DIAL, 0-300 PSIG

Note: The calibration certificate of the pressure gauge shall be checked and verified prior to use.

For convenience, the entire testing procedures have been divided into various parts as below:

Tower

Podium

7.4.4    Ensure the flow and pressure at the outlet of branch pipe.

  1. Safety:
  1. All PPE such as helmet, safety shoes, harness, gloves, etc., shall be used by the personnel, as required.
  1. Warning signs shall be placed at required location during pressure testing of pipe work.
  1. Only experienced and skilled personnel shall be engaged for carrying out the pressure testing work.
  1. All other precautions shall be followed as per established project safety procedures.
  1. Safety officer shall check and ensure all safety measures are followed as required.
  1. All concerned shall be notified prior to testing activities are commenced.
  1. Attachment:
  1. Testing and Commissioning certificate for sprinkler system.
  1. Testing and Commissioning certificate for wet riser system.