Method Statement Title: Testing and Commissioning of VFD’s.

METHOD STATEMENT FOR LV SWITCHGEAR AND MOTOR CONTROL CENTER INSTALLATION
METHOD STATEMENT FOR LV SWITCHGEAR AND MOTOR CONTROL CENTER INSTALLATION

Method Statement Title: Testing and Commissioning of VFD’s.

1.0       Scope

1.1       This method statement details the Testing and Commissioning of VFD’s according to the specification section 15725.

Note:   A separate method statement is submitted for installation of MCC’s and     VFD’s. (Ref. ETA /MS/E-012)

2.0       Material

  • All the materials shall be as per approved material submittals.
  • Size and number of VFD’s shall be as per approved shop drawing and load schedule.
  • Identifications and labels.

3.0       Applicable Location

3.1       VFD’s at East & West Podium Heat Exchanger Room.

4.0       Instruments.

4.1       Insulation Resistance tester (Megger) with Variable Voltage selections.

  • Phase Sequence meter.

4.3       Multimeter.

Note : The calibration certificates of testing instruments shall be verified prior to usage and copies shall be included in the test reports.

  • Test Procedure:
  • Power Connection :
  • Megger the incoming and outgoing power cable & connections for

Insulation check & short circuit. Please note that the power cables in the VFD’s terminals must be disconnected during this test or it may damage the VFD’s.

  • Reconnect the cables and all power terminals shall be checked for tightness.
  • All the power cables shall be supported well so that the stress is not on the terminals.
  • All fuses and overloads shall be checked for correct sizes.

5.2       Control Connection :

  • All control connection terminals shall be checked for tightness and continuity.
  • The screens of the screened cables shall be checked for proper earthing.
  • All terminations shall be cross checked with the drawing.
  • Insulation Resistance Test using 500V Megger:
  • Check the tightness of connections.
  • Clean all the supporting insulators.
  • Isolate the cables on incoming and outgoing side.
  • Apply a megger voltage of 500Volts DC between Phases ‘R’ to earth for 1 min with Phase ‘Y’,’B’ & ‘N’ shorted and earthed and record the values.
  • Similarly continue the test and record the values for the other phases.
  • Pre-commissioning Test:
  • Check the incoming voltage & phase sequence before switching ‘ON’ the incomer.
  • Check control supply and stop lock provision and operation.
  • Check bypass starter operation with the motor disconnected.
  • Check VFD’s operation with the motor disconnected, from the control keypad.
  • Set parameters as required and record the parameters.
  • Check VFD’s operations from keypad after connecting the motor, also check motor’s direction or rotation.
  • Check bypass starter operation with the motor connected, also check motor’s direction or rotation.
  • Check external (remote) control of the VFD’s.
  • Safety:
  • Only experienced and skilled personnel shall be engaged for testing.
  • Safety guards shall be in place and secured prior to start-up.
  • Warning signs and tapes shall be placed during start-up and commissioning as required.
  • All safety procedures shall be followed in accordance with the project health and safety plan.
  • Safety officer shall check and ensure all safety precautions as followed.
  • Records:
  • Site Test Reports.
  • Calibration certificates of testing instruments.

9.0       Reference:

  • Specification Section 15725.
  • Approved Drawings.

10.0     Enclosures:

10.1     Site Commissioning Report for VFD’s.

By Md Abu Zaed Khan

Hello, this is Engr. Zaed Khan Planning Engineer, Associate member of Society of Engineers UAE. Expert in construction project planning, FIDIC red book, computation of extension of time claim, Contract agreement and contractual letters.

Leave a comment

Your email address will not be published. Required fields are marked *

Exit mobile version