Risk Assessment for Emergency Lighting system

Method Statement Title: Testing and Commissioning of Fire Alarm System

Method Statement Title: Testing and Commissioning of Fire Alarm System

1.0       Scope

This method statement details the method of Testing and commissioning of  Fire Alarm  System, as per Project Specification 16721

            Note

            A separate Method Statement Ref. ETA/MS/E- 018 shall be submitted for Installation of  the Fire Alarm System.

2.0       Material

  • All materials shall be as per approved material submittals .
  • Sizes of FP200 cable shall be as per approved shop drawings / system manufacturers recommendation.

2.3       Type of FA device shall be as per approved shop drawing.

3.0       Applicable Location

            3.1       Tower E1, E2, E3, W1, W2, W3,Villas and Podium Areas.

4.0       Method

Find attached the manufacturer representative’s detailed method statement and test formats for testing and commissioning of Fire Alarm System covering the mechanical checks, insulation resistance measurement, switching ON the unit. Programming and testing

The whole system will be commissioned and certified by the manufacturer’s representative before handing over.

5.0       Records

            5.1       Commissioning procedure with test results in attached format.

            5.2       Inspection request duly signed-off by NMX and Consultant.

            5.3       Certification of installation by SIBCA

6.0       Attachment

6.1       Manufacturer’s representative method statement detailing the pre-commissioning and commissioning procedures, including test formats

Leave a Comment

Your email address will not be published. Required fields are marked *