Method Statement Title: Start-up and Commissioning of Fire Water Pumps

3-tips-for-Fire-Pump

3-tips-for-Fire-Pump

Method Statement Title: Start-up and Commissioning of Fire Water Pumps

Scope

The scope of this Method Statement is to define the method of Start-up and Commissioning of Fire Water Pumps installed within Burj Dubai – The Residences, in accordance with the Specification Sections 15500 applicable NFPA and manufacturer’s instructions attached.

            Note

  1. The Testing and Commissioning of Fire Fighting System will be covered under a separate Method Statement Ref.ETA/MS/P-14. This will also include the required test formats.

2.0       Material

            Refer to Appendix 1 – Schedule of  Fire Water Pumps.

3.0       Test Equipment

            3.2       Clamp Meter

            Note

            The calibration certificates of testing instruments shall be verified prior to usage and copies shall be included in the test reports.

4.0       Pre-commissioning checks prior to start-up

4.1       Mechanical

                        4.1.1    Check and inspect the installation of Fire Water Pump is complete, verify the installation as per approved drawings.

                        4.1.2    Verify compliance to the attached manufacturer’s installation instructions.

4.1.4    Check and ensure adequate clearance available for service and maintenance of pumps and motors.

                        4.1.5    Check the installation is coordinated with other services.

                        4.1.6    Ensure the shipping bolts / chambers are removed. 

                        4.1.11  Check the alignment is completed as per manufacturer’s instructions.

4.1.12  Check and verify the water level in the water tank is full.

            4.2       Electrical

4.2.1    Check all power cabling and control wiring is completed and dressed neatly.    

                        4.2.2    Check the power isolator is fixed close to the pump motor for emergency stop and power isolation.

4.2.3    Check all terminations are completed and tightened as required.

                        4.2.4    Check the grounding connections are completed and tightened as required.

                        4.2.5    Ensure the overload protections are set correctly as per the pump motor load current.

                        4.2.6    Ensure all identification tags and labeling works are complete.

5.0       Start-up and Testing

6.0       Safety

            6.1       Only experienced and skilled personnel shall be engaged for start-up and commissioning of chilled water pumps.

            6.2       Safety guards shall be in place and secured prior to start-up.

            6.3       Cable test reports shall be verified prior to energisation.

            6.4       Warning signs and tapes shall be placed during start-up and commissioning as required.

            6.5       All safety procedures shall be followed in accordance with the project health and safety plan.

            6.6       Safety Officer shall check and ensure all safety precautions are followed.

7.0       Records

7.1       WIR (for Witness of start-up and commissioning) duly signed by NMX and Consultants

            7.2       Signed-off pre-commissioning check lists

            7.3       Commissioning reports

            7.4       Calibration certificates of testing instruments

8.0       References

            8.1       Specification Sections 15500

            8.3       Manufacturer’s start-up and commissioning instructions.

            8.4       Approved Fire Water Pump submittals / drawings.

            8.5       Approved shop drawings.

9.0       Attachments

            9.1       Annexure-I Schedule of Pumps

            9.2       Pre-commissioning checklist

            9.3       Plant performance test sheet.