Method Statement Title: Installation, Testing and Commissioning of Sub Main Distribution Boards (SMDB’s)

METHOD STATEMENT FOR LV SWITCHGEAR AND MOTOR CONTROL CENTER INSTALLATION

METHOD STATEMENT FOR LV SWITCHGEAR AND MOTOR CONTROL CENTER INSTALLATION

1.0       Scope

  1. This method statement details the method of Installation, Testing & Commissioning of Sub Main Distribution Boards (SMDBs) according to the Specification Section 16442.

2.0       Material

3.0       Applicable Location

4.0       Method

4.1       Storage  

4.2       Installation

5.0       Testing & Commissioning:

            5.1       Instruments.

Note : The instruments used for  testing and commissioning shall be checked and ensured that they are calibrated and the current valid calibration reports are filed for record.

          5.2         Method

6.0       Safety

6.1       Safety Officer shall ensure that the technicians have undergone safety

            induction program.

                        avoid any violation on the same.

            same shall be ensured.

            procedures.

7.0       Records

            7.1       Commissioning check list and test format at attached.

            7.2       Inspection request duly signed-off by NMX and Consultant.