Method Statement Title: Installation of G.I. & PVC Conduiting on Surface

METHOD STATEMENT FOR ELECTRICAL PVC CONDUITS INSTALLATION

METHOD STATEMENT FOR ELECTRICAL PVC CONDUITS INSTALLATION

Method Statement Title: Installation of G.I. & PVC Conduiting on Surface

1.0     Scope :

  1. This method statement details the method of installation of G.I. Conduit and PVC Conduit on surface.

2.0     Material :

2.2       Sizes of Conduits to be used are 20mm dia to 50mm dia.

3.0     Applicable Location :

3.3       PVC Conduits are used only false ceiling areas.

4.0     Method :

4.1.1     Conduit shall be lowered not dropped to the ground. 

4.1.4     Conduits shall be protected from direct sunlight and moisture to avoid deterioration.

4.1.5.    Conduits shall be stored with proper end caps.

4.1.6     Conduits shall be stacked size wise.

4.2       Installation :

4.2.8     Conduits are fixed to the building fabric by means of distance bars saddle with appropriate metal screws and plugs.  A space of 3mm minimum shall be maintained between conduit and the building surface.

                        Check all mechanical connections are internally smooth for pulling wiring in no burrs or sharp edge will be allowed.

4.2.9     The route of this steel conduits are restricted to horizontal and vertical runs except for the areas where approved to follow the line of an architecture.

4.2.11   Ensure the Conduit installations are in straight line.

4.2.12   Conduits shall be fixed so that no water enters, if it is not practicable a 3mm hole is drilled at the lowest point of the conduit to drain the water out.

4.2.14   Wherever necessary draw wires shall be pulled into conduit runs and kept at pull boxes for future use.

4.2.15   Any rusting of steel conduits occurred during construction shall be removed.

            4.2.16   Inspection shall be offered for ETA QA verification.

5.0     Safety : 

All safety precautions shall be followed as per established project safety plan and procedure. 

6.0     Records :

6.1       Work Inspection Request (WIR) duly signed-off by NMX and Consultant.