METHOD STATEMENT Installation of Axial Fans

FAN STATIC CHECK SHEET
FAN STATIC CHECK SHEET

Contents:

  1. Objective
  2.  Scope
  3. References
  4. Material
  5. Material Procurement, Handling and Storage
  6. Procedure of Works
  1. Objective

This method statement provides information concerning the method of construction to ensure compliance with contract requirements, drawing, technical specification and quality control to provide a successful installation, testing, and commissioning of the Installation of Axial Fans.

  • Scope

HAC shall supply and install in accordance with the specification of material and workmanship of Axial Fans under full supervision of the supplier.

HAC shall complete install works, testing, witness testing at the site by the engineer, testing and commissioning of the Axial Fans.

  • References
  • Contract Specifications.
  • Material Submittal.
  • Technical Literature for Manufacturer.
  • Design Drawings.
  • Shop Drawings.
  • Latest edition of SMACNA Duct Construction Standards.
  • SCG comments on HAC clarifications.
  • Material
  • Axial Fans (e.g. Parking Supply & Exhaust Fans, Pressurization Fans, etc).
  • Material Procurement, Handling and Storage
  • Upon approval of the material and shop drawing submittals, Contractor shall survey the QTY including supporting system as per project schedule.
  •   Upon delivery to site, all fans shall be stored indoor, in a clean, dry and ventilated place.
  • For the lifting use a hoist crane or a fork-lift, inserting the hooks in the holes shown on the tags, using soft tissue strips, or with a fork truck.
  • Monthly, new grease must be added through the greasing point, turning the impeller by hand (about 100 turns) to avoid rusting from contact on the bearings.
  • Procedure of works
  • HAC carries out works as per approved Method Statement, drawings, etc.
  • The working area shall be protected as per risk assessment and HS&E plan.
  • The first thing you do on getting the fan is to read the manual carefully (if possible, with the fan nearby).
  • Make sure for the direction of the fans, fans data are correct.
  • Position the fan in such a way to assure a minimum space for the maintenance and repair work.
  • Silencers should be installed directly to the fans (if any).
  • For fans with inlet not ducted the distance “D” from the wall must be higher or at least equal to the inlet diameter.
  • The foundation should, by preference, be made in reinforced concrete and its minimum weight must to be four times the weight of the rotating mass (around double the total static weight), if the fan is installed on a metallic structure, make sure that it is solid.
  • The AP fans and gravity dampers are suitable for a direct wall mounting, or with steel adaptor.
  • The foundations or support structure must be level to prevent any damaging vibrations.
  • Take the anti-vibrations support, lift up the fan and install the anti-vibrations supports.
  • Before to start the fan it is important to check that the blades pitch is the required one, in case of wrong blades pitch, call the supplier.

Before connecting the power supply cable to the fan’s connection box, check that the line voltage is the same as the one shown on the motor’s data plate.

By Md Abu Zaed Khan

Hello, this is Engr. Zaed Khan Planning Engineer, Associate member of Society of Engineers UAE. Expert in construction project planning, FIDIC red book, computation of extension of time claim, Contract agreement and contractual letters.

Leave a comment

Your email address will not be published. Required fields are marked *

Exit mobile version