Site icon The Engineers Blog

METHOD STATEMENT FOR PLACING OF SELECT FILL

ACTIVITY HAZARD ANALYSIS PLACING OF SELECT FILL

ACTIVITY HAZARD ANALYSIS PLACING OF SELECT FILL

Table of Contents

  1. Purpose
  1. Responsibilities
  1. Attachments

1.0       Purpose

  1. To ensure that placing of select fill material and related activities are executed safely and in accordance with the contract requirements and that all quality assurance / control activities are conducted in a systematic manner, works are inspected and conformance is verified and documented.

2.0       Scope Of  Work

3.0   Definitions

3.1     CM                 Construction Manager

3.2      PE / SE         Project Engineer / Site Engineer

3.3      CS                 Chief Surveyor

3.4      ME                Material Engineer

3.5      ESHO            Environmental, Safety, and Heath Officer     

4.0     References

4.1   Specifications:             Civil Specifications Sections 200.9, 331.7

4.2    Drawings:                    Vol 2 – Section 8 – Part A – General and Topographic Survey

                                                Vol 2 – Section 8 – Part B – Civil, Mechanical and Navaids

Vol 2 – Section 8 – Part C – Surface Profiles and Pavement

       Geometry

 

7.0  Safety

8.0     Prior Activities

8.1  The Surveyor will locate and mark all live services that are present in the site (This       includes above ground services as well as buried services). These services (Electric, Telephone, Gas Oil, Chemical, Water, etc) will be clearly marked using stakes and warning tapes. Near these services, special precautions will be undertaken and coordination with the Engineer will be carried out to avoid any damages during the filling and compaction process. Any existing service, if exposed during previous excavation will be clearly marked, protected, and properly supported during all activities

8.2   The surveyor will verify that existing formation level is within +/- 25 mm tolerance as required by Clause 201.2.7 and table 331.12.1 The Surveyor will prepare plans and sections accordingly.

Select fill material will be carried out to comply with the requirements of latest and approved OAJ-JV Inspection test Plan 1008-OAJ-ITP-1002 which in turn reflects the testing requirements of the Specifications.

   levels and mark fill levels as required and as per specifications. The existing formation will be prepared and proof rolled according to table 331.7.1 of the Specifications. Afterwards, the existing layer will be pre-wetted to increase bonding with the new one.

Clauses 200.9 and 201.3.10. Additional layer of select fill material will be placed in the same method as described above, up to the required elevation as shown on the Drawings.

10.0       Responsibilities

  1. The CM will coordinate with SE and ensure that the necessary resources to implement the approved method statement, Job and Activity Hazard Analysis have been allocated to the task.
  1. The SE will ensure that the site preparation activities are conducted according to the approved method statement, JHA, AHA and all in-situ tests as required in the ITP are implemented.
  1. The ME will ensure that the materials being used are in accordance to the project specifications, the approved method statement and the ITP.

It is the Site Supervisor’s duty to organize the work in a safe manner to ensure that safety and protective equipment are being properly utilized.  He must also assure the AHA & JHA are implemented and the method statement procedure is followed and the ITP is applied.

Exit mobile version