CONTENTS
- 1.0 PURPOSE
- 2.0 SCOPE
- 3.0 REFERENCES
- 4.0 DEFINITIONS
- 5.0 RESPONSIBILITIES
- 6.0 EQUIPMENTS
- 7.0 PROCEDURE
- 8.0 ATTACHMENTS
1.0 PURPOSE
- This method statement is applicable for the Installation, Testing & Commissioning of External Fire Hydrant for the project as mentioned in the Specifications & Approved Shop Drawings.
2.0 SCOPE
- This method Statement shall cover the Supply, Installation, Testing & Commissioning of External Fire Hydrant in line with project requirements as indicated in the Approved Shop Drawings, specifications & manufacturer’s instructions.
3.1 Latest Approved shop drawings intended for Fire Fighting System
3.2 Specifications
- Project Quality Plan
- Project HSE Plan
- Material Approval
- Approved Method Statement for Installation & Testing for Fire Fighting System & Accessories
4.0 DEFINITIONS
- PQP : Project Quality Plan
- PSP : Project Safety Plan
- QCP : Quality Control Procedure
- HSE : Health, Safety and Environment
- MS : Method Statement
- ITP : Inspection Test Plan
- QA/QC : Quality Assurance / Quality Control Engineer.
- WIR : Inspection and Test Request
- MIR : Material Inspection Request
- UPVC Class E : Ultra polyvinyl chloride
- UPVC : Ultra polyvinyl chloride
- HDPE : High density polyethylene
- PEX PIPE : Cross-linked Polyethylene
- G.I. Pipe : Galvanized Iron Pipe
5.0 RESPONSIBILITIES:
5.1 Project Manager
5.2 Construction Manager
5.3 Site Engineer
5.4 QA/QC Engineer (MEP):
5.6 Safety Officer
5.7 Store Keeper (SK)
6.0 EQUIPMENTS
Following tools shall be arranged before starting the job.
7.0 PROCEDURE
Ø Work Sequence/Procedure
- General Requirements
- External Fire Hydrant to be inspected upon receipt & approved by the engineer prior in proceeding with the installation through MIR. Any discrepancies, damages etc., should be reported to the supplier for rectification or replacement & to be removed from site immediately.
7.2 Delivery & Storage
7.2.1 Material Transport/ Delivery
7.3 Storage
7.3.1 Storage on Site Store
7.4 Sequence of Installation for the External Fire Hydrant
7.4.1 Safety
7.4.2 Pre- Installation Procedure
7.4.3.2.2 Installation Procedure of Butterfly Valves:
7.4.4. Testing & Commissioning Procedures
7.4.4.1 Visual Inspection & Testing Procedure
8.0. ATTACHMENTS
8.1. Inspection & Test Plan
8.2. Installation Check Sheet
- Testing & Commissioning Check Sheet
Risk Assessment