Method Statement for Excavation and Foundation Preparation for Building Structures

Building Footing

Building Footing

Table of Contents

  1. Purpose
  1. Responsibilities
  1. Attachments

 

1.0       Purpose

  1. To ensure that all excavation and foundation preparation of building activities are executed safely and in accordance with the contract requirements and that all quality assurance / control activities are conducted in a systematic manner, works are inspected and conformance is verified and documented.

2.0       Scope of Work

3.0       Definitions

3.4    ME                  Material Engineer

3.5    ESHO              Environmental, Safety, and Heath Officer

3.6    ITP                  Inspection Testing Plan

3.7    AHA                 Activity Hazard Analysis

3.8    JHA                 Job Hazard Analysis  

4.1    Specifications:             Vol. 3 – Section 9 – Part A – General Civil &Mechanical  

                                             Infrastructure.

4.2    Drawings                     Vol. 2 – Section 8 – Part D Architectural & Structural

4.3    Bills of Quantities         Bills 12, 13, 14, 15, 16, 17 & 18

 

7.0       Safety

8.0       Prior Activities

   9.1  Excavations shall be carried according to the lines and grades indicated on the    approved shop drawings by using Excavator as per clause 201.2.1

   9.2  Excavations dimensions will allow for the necessary working distance around the   structure to permit the erection and removal of scaffolding and formwork (approx. 2m from concrete edge).

   9.4   Stock area for soil that might be reused shall be arranged .

9.5    The bottom of excavation shall be watered, leveled and compacted.

9.6    The formation level shall be examined and soft spots , deleterious or loose materials  

            shall be removed.

9.7   Bottom level of excavation and compaction will then be checked for approval by the Engineer’s Inspectors before any further activities are carried out as per clause 201.2.8

10.0   Responsibilities

  1. The CM will coordinate with SE to ensure that the necessary resources to implement the approved Method Statement, JHA and AHA have been allocated to the task.
  1. The SE will ensure that the site preparation activities are conducted according to the approved Method Statement, JHA and AHA.  The SE will also ensure that all in-situ tests, as required by the ITP are implemented.
  1. The ME will ensure that the materials being used are in accordance with the Project Specifications and approved Material Submittals.
  1. It is the site supervisors responsibility to organize the work in a safe manner to ensure that safety and protective equipment are being properly utilized.  He must also ensure that the AHA and JHA are implemented and the approved Method Statement procedure is followed and the ITP is applied.