uPVC High Pressure Water Supply Piping System Installation Procedure

METHOD STATEMENT FOR Drainage Piping System

METHOD STATEMENT FOR Drainage Piping System

CONTENTS

CONTENTS………………………………………………………………………………………………………….

1.0       Scope……………………………………………………………………………………………………. 3

2.0     REFERENCES……………………………………………………………………………………………………………………………………………………………..3

3.0       Responsibilities………………………………………………………………………………… 3

4.0       SEQUENCING………………………………………………………………………………………….. 4

5.0       CONSTRUCTION PROCEDURES……………………………………………………………… 4

6.0       TESTING………………………………………………………………………………………………… 5

7.0      EQUPMENT.……………………………………………………………………………………………………………………………………..5

8.0       Materials……………………………………………………………………………………………. 5

9.0       Environmental Considerations…………………………………………………… 6

10.0    Attachments……………………………………………………………………………………… 6

Attachment 1: Key to Safety Symbols…………………………………………………………………………….. 7

This method statment describe the specfic safe working method which will be use by Orasccom to carry out the Drainig Piping System , it gives details of how the work will be carried out , what health and safty issues and controls are involved.

  • Construction Manager:
    • Assigning tasks of responsibilities to senior site engineers.
    • Monitoring adherence to project schedule.
    • Expeding areas of concern to best achive project schedule.
  • Senior Site Engineer :
    • Assigning areas of responsibilities to site engineers.
  • Site Engineers :                     
    • Assigning areas of responsibilities to foreman.
    • Continuous montoring of all aspects , and follow activates and co-ordinate with another activities due to any Damage of another works.
    • Inspection of  any installed Drainig pipes and fittings.
    • Liasing  with QC Engineers regarding works progression and availabilty for hold point inspections.
  • Mechanical Quality Control Engineers :
    • Ongoing inspection of all aspects of  the installation works.
    • Informaing consultant by works inspection request as and when his presence is required to carry out inspections.
    • Follow the inspected works which approved by the consultant to prevent any damage and reported it by internal site instruction .
  • Sequencing.
    • Shop drawings approval.
    • Material approval.
    • Levelling and arrange with another spaces.
    • Installation pipes with its fittings.
    • Testing according the project specifications.
  • Construction Procedures
  • 5.1 installation preparation:
  • Follow the shop drawings to determine the routing, size, dimension, slop and exact location of the draining pipes.
  • All Material shall be new and installed in a first class manner.
  • All Draining piping unless otherwise indicated or required by code , to be pitched at a minmum rate of  1:100  in direction on flow. Branch connection to stack or main drains shall not made in manner which will permit backflow.
  • All vent piping shall br arranged to drain any condensate back to waste piping.
  • The open ends of the installed pipes should be closed to prevent entrance of foreign materials in the pipeline.
  • 5.2 Jointing of UPVC Pipes and fittings :
  • Cutting the pipes should be perpendicular to the pipe axis if pipe sludge are used.
  • A chamfer should be performed with suitable tool , in such a way as to avoid damage to gasket during the jointing stage.
  • The end of pipes and connection should be clean before the graft joint is made.
  • For ease of shank insertion, the part to be jointed with suitable lubrication material.
  • Mark depth of entry the tail of pipe into the spigot and align the mark.
  • Thoroughly abrade spigot and socket bonding surface using sandpaper.
  • Check the position and the condition of the rubber gasket inserted inside.
  • 5.3 For underground draining pipe :
  • Excavate the trench according to the trench detail shown in the drawings (Width, Depth).
  • Put a suitable bedding material layer , bedding to be thoroughly compact in layers not exceeding 150mm to give uniform bed.
  • Backfill the trench above the pipe in layer 300mm thick each layer well rammed with the suitable backfilling material according to the project specfication and method of statment .
  • Testing
  • Back fill along the pipe except above the pipe joints and fitting untill we proceed with the pipe test.
  • Test of the pipe according to the project specification section 02530 Division 3.6
  • Subject systems to  water pressure test to prove tightness and to flow test to prove freedom from obstruction.
  • Close all opening with plugs and fill system to point of overflow at highest opening.
  • Vent all air and ensure that water reaches all parts of system to be tested.
  • All sections to be tested to not less than 1 m head of water at highest point for at least 30 minutes.
  • Inspect all joints and pipes whilst under pressure and correct leaks or detective joints by replacing with new joints and materials .
  • Repeat test after corrections are made and untill systems are proven tight.
  • Equipment:
  • Plumber tool box.
  • Welding Device and Tools.
  • Personal tools.
  • EEPCO UPVC fittings for draining system.

Approved Transmittal No: PKG #75&76 – MT- PL – 00043- Rev. 01

  • MISR EL HEGAZ CO.  UPVC pipes for draining systems.

Approved Transmittal No : PKG #75&76 – MT- PL – 00042- Rev. 01

  • Considerations

               All as per OCI procedures:

  • HSEP 01 – Evaluation of Environmental Aspects
  • HSEP 02 – Environmental Programme

Key to Safety Symbols

Leave a Comment

Your email address will not be published. Required fields are marked *

Scroll to Top