uPVC High Pressure Water Supply Piping System Installation Procedure

Method Statement for Drainage Piping System

METHOD STATEMENT FOR Drainage Piping System

METHOD STATEMENT FOR Drainage Piping System

CONTENTS

CONTENTS………………………………………………………………………………………………………….

1.0       Scope……………………………………………………………………………………………………. 3

2.0     REFERENCES……………………………………………………………………………………………………………………………………………………………..3

3.0       Responsibilities………………………………………………………………………………… 3

4.0       SEQUENCING………………………………………………………………………………………….. 4

5.0       CONSTRUCTION PROCEDURES……………………………………………………………… 4

6.0       TESTING………………………………………………………………………………………………… 5

7.0      EQUPMENT.……………………………………………………………………………………………………………………………………..5

8.0       Materials……………………………………………………………………………………………. 5

9.0       Environmental Considerations…………………………………………………… 6

10.0    Attachments……………………………………………………………………………………… 6

Attachment 1: Key to Safety Symbols…………………………………………………………………………….. 7

This method statment describe the specfic safe working method which will be use by Orasccom to carry out the Drainig Piping System , it gives details of how the work will be carried out , what health and safty issues and controls are involved.

  • Construction Manager:
    • Assigning tasks of responsibilities to senior site engineers.
    • Monitoring adherence to project schedule.
    • Expeding areas of concern to best achive project schedule.
  • Senior Site Engineer :
    • Assigning areas of responsibilities to site engineers.
  • Site Engineers :                     
    • Assigning areas of responsibilities to foreman.
    • Continuous montoring of all aspects , and follow activates and co-ordinate with another activities due to any Damage of another works.
    • Inspection of  any installed Drainig pipes and fittings.
    • Liasing  with QC Engineers regarding works progression and availabilty for hold point inspections.
  • Mechanical Quality Control Engineers :
    • Ongoing inspection of all aspects of  the installation works.
    • Informaing consultant by works inspection request as and when his presence is required to carry out inspections.
    • Follow the inspected works which approved by the consultant to prevent any damage and reported it by internal site instruction .
  • Sequencing.
    • Shop drawings approval.
    • Material approval.
    • Levelling and arrange with another spaces.
    • Installation pipes with its fittings.
    • Testing according the project specifications.
  • Construction Procedures
  • 5.1 installation preparation:
  • Follow the shop drawings to determine the routing, size, dimension, slop and exact location of the draining pipes.
  • All Material shall be new and installed in a first class manner.
  • All Draining piping unless otherwise indicated or required by code , to be pitched at a minmum rate of  1:100  in direction on flow. Branch connection to stack or main drains shall not made in manner which will permit backflow.
  • All vent piping shall br arranged to drain any condensate back to waste piping.
  • The open ends of the installed pipes should be closed to prevent entrance of foreign materials in the pipeline.
  • 5.2 Jointing of UPVC Pipes and fittings :
  • Cutting the pipes should be perpendicular to the pipe axis if pipe sludge are used.
  • A chamfer should be performed with suitable tool , in such a way as to avoid damage to gasket during the jointing stage.
  • The end of pipes and connection should be clean before the graft joint is made.
  • For ease of shank insertion, the part to be jointed with suitable lubrication material.
  • Mark depth of entry the tail of pipe into the spigot and align the mark.
  • Thoroughly abrade spigot and socket bonding surface using sandpaper.
  • Check the position and the condition of the rubber gasket inserted inside.
  • 5.3 For underground draining pipe :
  • Excavate the trench according to the trench detail shown in the drawings (Width, Depth).
  • Put a suitable bedding material layer , bedding to be thoroughly compact in layers not exceeding 150mm to give uniform bed.
  • Backfill the trench above the pipe in layer 300mm thick each layer well rammed with the suitable backfilling material according to the project specfication and method of statment .
  • Testing
  • Back fill along the pipe except above the pipe joints and fitting untill we proceed with the pipe test.
  • Test of the pipe according to the project specification section 02530 Division 3.6
  • Subject systems to  water pressure test to prove tightness and to flow test to prove freedom from obstruction.
  • Close all opening with plugs and fill system to point of overflow at highest opening.
  • Vent all air and ensure that water reaches all parts of system to be tested.
  • All sections to be tested to not less than 1 m head of water at highest point for at least 30 minutes.
  • Inspect all joints and pipes whilst under pressure and correct leaks or detective joints by replacing with new joints and materials .
  • Repeat test after corrections are made and untill systems are proven tight.
  • Equipment:
  • Plumber tool box.
  • Welding Device and Tools.
  • Personal tools.
  • EEPCO UPVC fittings for draining system.

Approved Transmittal No: PKG #75&76 – MT- PL – 00043- Rev. 01

  • MISR EL HEGAZ CO.  UPVC pipes for draining systems.

Approved Transmittal No : PKG #75&76 – MT- PL – 00042- Rev. 01

  • Considerations

               All as per OCI procedures:

  • HSEP 01 – Evaluation of Environmental Aspects
  • HSEP 02 – Environmental Programme

Key to Safety Symbols

EngineersBlog Home | Method Statement for Drainage Piping System – METHOD STATEMENT FOR Drainage Piping System

{ “@context”: “https://schema.org”, “@type”: “Article”, “headline”: “Method Statement for Drainage Piping System – METHOD STATEMENT FOR Drainage Piping System”, “description”: “This method statement describe the specific safe working method which will be use by Orasccom to carry out the Draining Piping System , it”, “author”: { “@type”: “Person”, “name”: “Md Abu Zaed Khan” }, “datePublished”: “2022-11-06T22:18:26+04:00”, “dateModified”: “2022-11-06T22:19:03+04:00”, “url”: “https://engineersblog.net/method-statement-for-drainage-piping-system/” } { “@context”: “https://schema.org”, “@type”: “BreadcrumbList”, “itemListElement”: [ { “@type”: “ListItem”, “position”: 1, “name”: “Home”, “item”: “https://engineersblog.net/” }, { “@type”: “ListItem”, “position”: 2, “name”: “Method of Statement”, “item”: “https://engineersblog.net/method-of-statement/” }, { “@type”: “ListItem”, “position”: 3, “name”: “Method Statement for Drainage Piping System – METHOD STATEMENT FOR Drainage Piping System”, “item”: “https://engineersblog.net/method-statement-for-drainage-piping-system/” } ] }

Leave a Comment

Your email address will not be published. Required fields are marked *

Scroll to Top