Method Statement for Construction of Ducts for Fire & Water Supply Network

METHOD STATEMENT FOR MV CABLE PULLING AND INSTALLATION
METHOD STATEMENT FOR MV CABLE PULLING AND INSTALLATION

CONTENTS

  1. Scope of Work
  • Definitions
  • References
  • Subcontractors
  • Materials
  • Plant  & Equipment
  • Safety
  • Prior Activities
  • Procedure
  1. Responsibilities
  1. Attachments

 1. Scope:

1.1This Method Statement covers the construction of ducts for fire and water supply network under taxiways, roads and wherever needed.

2. Definitions:

2.1    MS: STM Method Statement : Ducts for fire and water supply networks.
  
2.2ITP  Inspection and Testing Plan
  
2.3PS-GCMI  Project Specifications-General, Civil and Mechanical Infrastructure
  
2.5UG   Underground
  

3. References:

3.1PS-GCMI : Section 901 Pipework
                    Section 901 : clause 901.3.10 Concrete surround
  
3.2PS-GCMI : Section 401: Clause 401.7 and 401.9, Concrete grade and Quality Control
                    Clauses 401.12, 401.13 Placing of concrete and Formwork
  
3.3PS-GCMI : Section 401: Clause 401.20.2: Application of protective coatings
  
3.4MS – 1005 Surveying
  
3.5MS -1004 Dewatering
  
3.6MS -1008 Earthworks
  
3.7Inspection Testing plan to be submitted for approval

4. Subcontractors:

4.1N/A.

5.  Products:   

5.1GRP Pipes, dia 450mm and fittings as sleeves.
  
5.2Concrete class 40/20/S
  
5.3Brush-applied tanking membrane and Protection Board: Bitutex FBR and Bituboard Refer to Material submittal 1008-OAJ-FM-MSF-RO / STR 002 or similar approved.
  
5.4Lubrication soap for rubber rings
  
5.520 mm thickness fiber board.
  
5.6Teflon Spacers

6. Plant & Equipment:

6.1Dewatering Equipment (If required)
  
6.2Excavators, JCB
  
6.5Crane (if required).
  
6.7Concrete Mix Trucks
  
6.8Light Vehicles
  
6.9Concrete vibrators
  
6.10Surveying Instruments
  
6.12Ladders
  
6.13Concrete Barricades
  
6.15Flagging Tape/Warning Tape
  
6.16Concrete Formwork
  
6.17Concrete Temp. Gauge
  
6.18Slump cone, cube moulds

 7. Safety

7.1PS-GCMI Section 102: Clause 102.11, 102.12 and 102.14 General and Preliminary
  
7.2PS-GCMI Section 901 Clause 901.3: Trench Excavation and Backfill.  
7.3PS-GCMI Section 100: Clause 100.2 Airport Emergency And Safety
  
7.4OAJ JV Safety Manual
  
7.5Activity Hazard Analysis to be submitted for approval
7.6Safety Hazards and Precautions 
   a)- Strike UG Services:   Use Locator and/or hand excavation (trial holes)  
 b)-Excavation Collapse:   Batter sides to safe slope or provide shoring (as directed by Geotechnical Consultant) and subject to the Engineer’s approval.   Keep vehicles/equipment safely away from excavation edge   Keep spoil at least 2.0 meter away from edge   c)- Fall into excavation:   Provide fencing, guardrails or flagging tape around edges and night lights.   Provide safely fixed ladders (every 50m)   Provide banks man when operating equipment near excavation.   d)-Crane Accidents:   All cranes checked and certified   Operators professional and well experienced   Provide banks man when operating near excavation   Check load indicator, slings and wire ropes daily   e)- Falling Objects:   Stand clear during lifting operations   Wear hard hats   f)- Equipment & Vehicles:   Use Safety belts   Slow down and obey speed limits   Provide “back-ups” alarms   Provide banks man when operating equipment near excavation.   g)- Confined Space:           Check excavations for snakes and scorpions before entering trenches.   Take precautions against flooding   Develop rescue procedures

8. Prior Activities:

8.1Calibrate Surveying Instruments.  
8.2Check for Existing Utilities before excavation (Trial Holes).  
8.3Check all pipes free of cracks and chips or damage to liner.
8.4Prepare and get approval of Shop Drawings.
8.5Pipes transportation, handling and storage will strictly comply with the manufacturer’s instructions  
8.6In case of dewatering, proper water discharge away from work area will be provided. Permits will be obtained where needed.

.

 9. Procedure:

            All activities carried out will comply with the OAJ-JV Inspection Test Plan (1008-OAJ-ITP-1020) which reflects the testing requirements of the Contract and which will be submitted for approval.    

9.1Prepare the Shop Drawings and submit to the Engineer for approval prior to starting any excavation works. The actual location of ducts will then be determined and checked on Site. Any obstruction encountered will be reported to the Engineer and will be indicated in a revised shop drawing. A shop drawing will be issued for each section of line and will be subject to the Engineer’s approval.  
Note:Only the drawings marked as approved “Issued for Construction” are allowed to be used by the Site Staff.  
9.2Survey will be conducted according to MS-1005  
9.3  Dewatering (If required) will be conducted according to MS-1004.  
9.4Excavation will be conducted to the proper formation level according to MS-1008.
  
Note:The Engineer’s Inspector will be notified if any areas are over excavated or unsuitable materials are encountered, in which case replacement material will be used.
  
9.5The trench formation shall be compacted to 98% MDD.
  
9.6The formation level will be to the required lines and grades as detailed in the approved Shop Drawings.
  
Note:Formation compaction is a Hold Point and will be confirmed by the Engineer’s Inspector before proceeding with blinding concrete.
  
9.7Blinding concrete class 30/20/S and pipe installation will be undertaken after the compaction and the Engineer’s approval is given.  
Note:The pipe installation is a hold point and lines and levels must be checked and approved by the Engineer’s Inspector before other work proceeds.  Any adjustment in the line and grade shall be made by scrapping away or filling and tampering in under the Barrel of the pipe.  
9.8Concrete cradles are then placed to support the pipe and allow easy adjustment to mentioned correct lines and levels.  
9.9The pipes will be fixed over the cradles as per the required levels and tightened to the fixed hooks to prevent any movement or uplifts during concrete casting according to Manufacturer’s recommendation. 20mm thickness compressible filler board will be installed at each joint.
9.12Levels will be checked to confirm accuracy as per approved shop drawings followed by the fixing of an approved shutter as per clause 401.13 “Formwork”.  
9.13Once all pre-pour aspects are checked and found acceptable by the Engineer’s Inspectors, concrete grade 40/20/S mass concrete will be poured according to clause 401.12 “Placing of concrete” to the levels shown on the shop drawings.
  
9.14Pipeline will then be visually checked by torch and mirror.
  
9.15As soon as is practicable, all concrete shall be cured by the application of approved concrete curing membrane or materials.
  
9.16All foreign materials shall be thoroughly cleaned after striking the formwork (Clause 401.13.5). Brush-applied tanking membrane will be applied according to specifications and protection board installed as per clause 401.20.2 and as per manufacturer’s recommendations.

 Backfilling:

9.17Backfilling will proceed in layers in accordance with MS-1008 only after striking the formwork and after the concrete has gained enough strength to sustain the filling material load and compaction.
  

 10. Responsibilities:

10.1The CM will coordinate with SE and ensure that the necessary resources to implement the approved method statement and ITP have been allocated to the task.
  
10.2It is the Site Supervisor’s duty to organize the work in a safe manner to ensure that safety and protective equipment are being properly utilized.  He must also assure the method statement procedure is followed and must observe the Hold-points and notify the Engineer for inspection.
  
10.3It is the worker’s duty to properly wear the protective equipment provided and obey all safety rules.  They must also perform the work as described in the method statement procedure.  
10.4The SE will ensure that the site preparation activities are conducted according to the approved method statement and all in-situ tests according to the ITP are implemented.  
10.5The ME will ensure that the materials being used are in accordance to the project specifications, the approved method statement and the ITP.

By Md Abu Zaed Khan

Hello, this is Engr. Zaed Khan Planning Engineer, Associate member of Society of Engineers UAE. Expert in construction project planning, FIDIC red book, computation of extension of time claim, Contract agreement and contractual letters.

Leave a comment

Your email address will not be published. Required fields are marked *

Exit mobile version