Site icon The Engineers Blog

Method Statement for Construction of Cast-in-Situ Concrete for Building Structures

ACTIVITY HAZARD ANALYSIS Construction of Cast-in-Situ Concrete for Building structure

ACTIVITY HAZARD ANALYSIS Construction of Cast-in-Situ Concrete for Building structure

CONTENTS

  1. Purpose
  1. Responsibilities
  1. Attachments
  1. Purpose
  1. To ensure that the Cast-In-Situ Concrete Building Structures are executed safely and in accordance with the contract requirements and that all quality assurance/control activities are conducted in a systematic manner, works are inspected and conformance is verified and documented.

3.1       CM      Construction Manager

3.2       SE       Site Engineer

            3.3       CS       Chief Surveyor

            3.4       ME       Material Engineer

            3.5       ESHO  Environmental, Safety, and Health Officer

            3.6       ITP      Inspection Testing Plan

            3.7       AHA     Activity Hazard Analysis

            3.8       JHA     Job Hazard Analysis

         4.1       Specifications:             Volume 3 – Section 9 – Part A – General, Civil and

                                                         Mechanical Infrastructure (Section 401)

            4.2       Drawings:                    Volume 2 – Section 8 – Part D – Architectural and Structural

            4.3       BOQ:                           Bill Nos. 12, 13, 14, 15, 16, & 17.

  1. Responsibilities
  1. The CM will coordinate with SE to ensure that the necessary resources to implement the approved method statement, JHA, and AHA have been allocated to the task.
  1. The SE will ensure that the site preparation activities are conducted according to the approved method statement, JHA and AHA.  The SE will also ensure that all in-situ tests, as required by the ITP, are implemented.
  1. The ME will ensure that the materials being used are in accordance with the project specifications and approved material submittals.
  1. It is the site supervisor’s responsibility to organize the work in a safe manner to ensure that safety and protective equipment are being properly utilized.  He must also ensure that the AHA and JHA are implemented and the approved Method Statement procedure is followed and the ITP is applied.
Exit mobile version