METHOD STATEMENT FOR CLOCK SYSTEM INSTALLATION
- TABLE OF CONTENTS
1. SCOPE
2. definitions
3. HEALTH AND SAFETY
4. OPERATION
5. installation and fixation
6. RESPONSIBILITIES
7. MANPOWER REQUIRED
8. MATERIALS REQUIREMENTS
9. EQUIPMENTs REQUIREMENTs
10. WASTE MANAGEMENT
11. SPECIAL CONTROL MEASURES
12. SUPPORTING DOCUMENTATION
13. DISTRIBUTION
1. SCOPE
- This procedure to clear the method of the supply, installations Clock system for the project.
- This document details the Clock system Installation:
- Preparation of work.
- Delivery and inspection upon arrival of material at site.
- Installation of the system.
2. definitions
PQP : Project Quality Plan
PSP : Project Safety Plan
QCP : Quality Control Procedure
HSE : Health, Safety and Environment
MS : Method Statement
ITP : Inspection Test Plan
QA/QC : Quality Assurance / Quality Control Engineer.
WIR : Inspection and Test Request
MIR : Material Verification Record.
3. HEALTH AND SAFETY
- Strictly followed as per the manufacturer’s Health and Safety recommendations for handling and use of the materials.
- Ensure all involved personnel shall be aware of the same.
- Specific safety measures have to follow as applicable, and all the safety measures are covered separately in the project safety plan.
4. OPERATION
- Material:
- Material used will be as approved by the Engineer.
- The sizes and routes routing will be as per the approved Shop Drawings.
- Storage and Protection:
- Deliver components parts to site, completely identified in accordance with shop and certified CAD Drawings prepared for this work.
- Store in accordance with the manufacturer’s instructions, above ground, properly protected from the weather and construction activities.
5. INSTALLATION and Fixation
- Pre-Installation:
- Make sure that civil clearance done prior to start the installation.
- Installation will be carried out as per manufacturer recommendations, Approved shop drawings and project specifications.
Ø Installation:
- Civil Clearance before start the installation of the IP Clock system (Clock & Panels).
- Check that all conduits for the Data of the IP Clock installed as per approved shop drawings, Specs., Wiring diagram & approved schematic Diagram.
- Check that all panels installed as per manufacturer recommendations and all wires Identified inside the panel.
- Check that the IP Clock system and its Accessories approved as per material submittal.
- Check that the location of the IP Clock / panels and the position set as per approved shop drawings.
- Check that the Installed IP Clock is the correct type.
- Refer to relevant IP Clock system drawing layouts and schematic diagrams for all components provided in this section for exact location and details of integration with other sub-systems.
- Check that the cameras setting and programmed as per project requirements and manufacturer recommendations.
- Installation of Wires:
- Install cables in raceways and cable trays except within consoles, back boxes, desks, and counters. Conceal raceway and cables except in unfinished spaces.
- Comply with requirements for raceways and boxes specified in Division 26 Section “Raceways, Boxes, Cable Tray, Cable Ladder and Trunking”.
- Conceal conductors and cables in accessible ceilings, walls, and floors where possible.
- Conceal wiring except in unfinished spaces.
- All new wiring on this project must be properly rated for the application.
- Cable to the new devices at new locations shall be installed in a neat and workmanlike manner, following the standard procedures used in the electrical contracting trade.
- Exposed wiring will not be permitted under any circumstances on this project.
- Any wiring, which is considered sloppy by the owner representative, shall be strictly unacceptable.
- Upon installation completion, a room-by-room test shall be conducted for every device in the system.
- A technician shall perform the test after school hours, and repairs shall be performed as needed at no cost to the Owner to any devices, which do not function correctly, including cable.
- A written room-by-room report following testing and repairs shall be prepared and submitted to the owner representative as per Specs.
- Installation and Attached manufacturer recommendation for the installation in Others Sections.
- Wiring within Enclosures:
- Bundle, lace, and train cables within enclosures. Connect to terminal points with no excess and without exceeding manufacturer’s limitations on bending radius.
- :
- Comply with requirements in Division 26 Section “Grounding and Bonding for Electrical Systems.” for grounding conductors and connectors.
- Comply with Electricity Wiring Regulations, Sections.
- Bond metallic equipment to the system grounding bus bar, using not smaller than the specified equipment grounding conductor by Electricity Wiring Regulations, Sections.
- Identification:
- Identify system components, wiring, and cabling complying with ADDC Electricity Wiring Regulations. Comply with requirements for identification specified in Division 26 Section “Identification for Electrical Systems.”
- Programming:
- After making sure all the system installed in correct way from Subcontractor and supplier, programming of the system must take place before final testing and commissioning according to Consultant requirement and scenario of the system.
- Testing and commissioning of the system submitted separately for this system mentioned all the procedure of Testing of the system and commissioning it.
- Technical Assistance:
- The installation supervising technician for the system trade shall instruct the CONSULTANT Engineer, and Construction Site Manager on the programming and correct operation of the system after the installation is completed.
- This instruction shall be scheduled at the convenience of the staff.
- All such instruction shall be properly recorded.
- WIR will be issued for Consultant approval upon making sure that the installation of the system equipment’s done as per approved shop drawings, approved specs and manufacturer recommendations.
6. RESPONSIBILITIES
Ø PROJECT MANAGER
- To ensure that all the preparation and application works are carried out according to the Contract Specification and with the approved drawings.
- To ensure that the progressing of works is carried out according to the planned program and as per the approved method of statement.
- To ensure that all the equipment and material required executing the work are available according to the planned construction program.
- To co-ordinate with the Main contractor, MEP coordinator, Safety Officer for a safe and proper execution of the works.
Ø SITE ENGINEER
- To ensure that the works are carried out according to the Contract Specification, approved method statement and the shop drawings.
- To provide all necessary information and distribute responsibilities to his construction.
- To monitor the progress of work in relation with the work program and to report to the Project Manager.
- To co-ordinate with the safety officer and to ensure that the works are carried out in safe practicing method.
Ø FOREMAN
- The foreman will carry out his duties by maintaining continuous coordination with the site engineer on daily basis, and ensure proper distribution of the work force on the required and planned locations.
- To ensure that his assistant foreman/ charge hand are aware of the job requirements and they have enough information to carry out their duties properly.
- To ensure that the daily work is progressing as planned and advice the site engineer of any requirement for additional resources.
- To ensure in consultation with the site engineer that the manpower involved in the works are moving as agreed and planned for the work.
- To control disposal of waste materials according to the instructions received from the site engineer.
- To ensure full coordination with the safety officer to maintain safe working and proper house keeping of the site, following the proved safety measures and further ensure that all his working team are aware of the same to prevent accident and losses.
- To inform the site engineer regarding areas ready for inspection.
- Foreman and the storekeeper are responsible for the distribution and control of materials.
Ø SAFETY ENGINEER
- Ensure the implementation of all the safety measures in accordance with the HSE plan and everybody aware of it for it’s proper implementation.
- Ensure all the implemented safety measures are adequate to maintain safe working on the site.
- Inspect all the site activities and train the person to prevent accidents and it’s proper implementation.
- Ensure that the site is maintained clean and tidy.
Ø TECHNICIAN FROM SUPPILER
- The carrying-out of work and the proper distribution of all the available resources in coordination with the sub-contractor Site Engineer on a daily basis.
- Daily reports of the works are achieved and coordinated for the future planning with the Site Engineer.
- Complying with the sub-contractor basic design practices, particularly those related to safety and engineering
- Meeting with any type of unforeseen incident or requirement and reporting the same to the Site Engineer immediately.
Ø STORE KEEPER
- Responsible for overall Store operations in making sure to store the material delivery to the site and keep it in suitable area that will keep the material in safe from rusty and damage.
- One who will acknowledge the receiving of materials at site in coordination with QA/QC and concerned Engineer.
7. MANPOWER REQUIRED
- Charge hand and Experienced Technicians
8. MATERIALS REQUIREMENTS
- CS Components and Accessories.
9. EQUIPMENTs REQUIREMENTs
- The Equipment that will be engaged for Clock System Installation will be as follows:
- Tools for fixing the control panel on a vertical surface.
- A small flat-bladed (terminal) screwdriver.
- A large Posi-drive screwdriver for internal screws
- A pair of wire cutters/strippers appropriate for the type of cable used,
- Ferules and ferruling tool for dressing the ends of cables (if stranded conductors are used),
- Pulling Spring
- Hammer
- Measuring Wheel.
- Drilling tools.
- Ladders.
- Scaffolding (to be provided by the contractor for the High level Area).
- Safety requirements tools such as safety shoes, safety helmet, safety glasses, fluorescent vest, and safety gloves to insure maximum ability of safe work and dust mask when required.
10. WASTE MANAGEMENT
- The Rubbish which would be created from our scope of works will be disposed to the designated dumping ground.
11. SPECIAL CONTROL MEASURES
- The following general control measures against Safety, Environment and Quality shall be required for our scope of work and special control measures are not applicable for us :
- Proper PPE must be worn at all time
- Permit to work at height > 2m where applicable
- Lifting operation permit (using crane) where applicable.
- Confined space permit where applicable.
- Approved work method statement and risk assessment will be made available to site.
- All workers doing the work shall be briefed on this method statement and risk assessment.
12. SUPPORTING DOCUMENTATION
- This method Statement should be read in conjunction with the below referenced documentations:
- ITP for Anti – termite Treatment.
- Insulation Resistance and continuity Test Report.
13. DISTRIBUTION
- Copy of this method statement shall be issued to the following for information/ action/ comments:
- Project Manager
- Site Engineer
- Foremen
- Safety Engineer
- Technician From Supplier
- Store Keeper



