Site icon The Engineers Blog

Method Statement for Backfilling of Precast Units

ACTIVITY HAZARD ANALYSIS Construction of Open Concrete Formed Channel

ACTIVITY HAZARD ANALYSIS Construction of Open Concrete Formed Channel

CONTENTS

  1. Purpose
  1. Responsibilities
  1. Attachments
  1. Purpose

1.1       To ensure that the backfilling of precast units such as subgrade drainage inspection chambers, communication pits, and electrical pits is executed safely and in accordance with the contract requirements and that all quality assurance/ control activities are conducted in a systematic manner, works are inspected and conformance is verified and documented.

Note:

  1. AGL Pits Backfilling Method Statement shall be submitted separately.
  1. Responsibilities
  1. The CM will coordinate with SE and ensure that all necessary resources to implement the approved method statement, JHA, and AHA have been allocated to the task.
  1. The SE will ensure that the site preparation activities are conducted according to the approved method statement, JHA and AHA.  The SE will also ensure that all in-situ tests, as required by the ITP, are implemented.
  1. The ME will ensure that the materials being used are in accordance with the project specifications and the approved material submittals.
  1. It is the site supervisor’s responsibility to organize the work in a safe manner to ensure that safety and protective equipment are being properly utilized.  He must also ensure that the AHA and JHA are implemented and the approved method statement procedure is followed and the ITP is applied.
Exit mobile version