METHOD STATEMENT DISTRIBUTION BOARDS

METHOD STATEMENT FOR LV SWITCHGEAR AND MOTOR CONTROL CENTER INSTALLATION

METHOD STATEMENT FOR LV SWITCHGEAR AND MOTOR CONTROL CENTER INSTALLATION

TABLE OF CONTENTS

  1. Scope / Objective
  1. Safety Lighting
    1. Task Lighting
    1. Emergency Arrangements
      1. General
      1. Fire Precautions
      1. Communication
    1. Risks Control
  2. Hazards / Risks
  3. 3rd Party Protection
  4. Environmental Considerations
  5. Definitions
  1. House Keeping
  1. Manpower Requirement & Supervision
  1. Material Requirement
  1. Plant & Equipment
    1. General
    1. Plant and Equipment Schedule
    1. Personnel Protective Equipment
    1. Power
    1. Working Platforms
  1. Q.C. Approvals and other Documentation
  1. Supporting Documentation
  1. Distribution
  1. Other Information
  1. Site Safety Engineers Approval
  1. Attachment – Sketches


    1.0    Revision Status
 Revision NoDatePrepared ByReviewed ByArabtech Approved  Revision Description 
 05/10/04    S.Georgiou   C.Ctorides  G.GeorghiouM.Pickup  
 116/11/04    S.Georgiou   C.Ctorides  G.GeorghiouM.Pickup  
 216/12/04    S.Georgiou   C.Ctorides  G.GeorghiouM.Pickup  
 324/03/05    S.Georgiou   C.Ctorides  K.MarneridesM.Pickup  
 44/04/05    S.Georgiou   C.Ctorides  K.MarneridesM.Pickup  
        
            


1.0     SCOPE / OBJECTIVES

This Method Statement covers the installation of Distribution Boards. This procedure is to define the method used to ensure that the Distribution Boards have been installed as per the contract requirement.

Work will be carried out only when all associated works of main contractor been verified that they have been completed.

4.0       HEALTH AND SAFETY HAZARDS.

Health and Safety procedure by Main Contractor and by A&P will be implemented for this job. The responsible safety officer as per A&P procedure will do a routine safety inspection.

  1. Safety Lighting.

Safety lights will be used in case of power failure ensuring the good illumination of the working area to aid evacuation if necessary.

Adequate lighting will be provided ensuring the good illumination of the working area. Task lighting, where required will consist of tripod mounted fluorescent light.

  1. Risk and Controls.
  1. Hazards / Risks

Relevant Risk Assesments (see Section 19 Attachments)

5.0       DEFINITIONS

              ATC  –           Arabtec Construction (LLC.)

              A&P –           A&P Paraskevaides and Partners LLC.

              M.S. –            Method Statements.

6.0     RESPONSIBILITIES / SUPERVISION

SURFACE MOUNTED

RECESSED MOUNTED

8.0           TRAINING

8.1       Tradesmen who will be used to perform the described work will be trained electricians and assistance. If deemed necessary specific team / individuals will undergo further training by the Production / Quality Assistance Departments.

9.0           WORKING HOURS

Normal working hours: 7.00 a.m to 5.00 pm

  1. HOUSE KEEPING

A&P personnel will clear work areas of scrap materials derived from their work on a daily basis ensuring a clean and healthy work environment and also to maintained free access and egress in the event of an emergency.

  1. MANPOWER REQUIREMENT & SUPERVISION

For the installation and wiring of a Distribution Board one (1no) electrician and one (1no) assistant is needed or as required to suit the project completion dated.

  1. MATERIAL REQUIRMENT

Materials requirement for this activity are: Distribution board, MCBs, rawl-bolds, screws.

  1. PLANT & EQUIPMENT REQUIREMENTS
  1.    General: Markers, drills, pliers, hammer, screw driver, cutter, spirit level, set of wrenches.
    1. Plant and equipment schedule: Ditto
      1.    Personnel Protective equipment:  All personnel should wear at all time safety shoes, helmet and coverall.
        1. Power: Single-phase normal power where it is needed.
          1.   Working Platforms: Stepladders as required within the specific work area.
  1. Q.C. APPROVAL AND OTHER DOCUMENTATION
  1. SUPPORTING DOCUMENTATION

Relevant Shop Drawings and Distribution Board Schedule.

  1. DISTRIBUTION
  1. OTHER INFORMATION

Not applicable

  1. SITE SAFETY ENGINEER’S APPROVAL

Risk Mitigation measures as identified in the Risk Assessments in Section 19 to be inspected at regular intervals through out the duration of the activity.

  1. ATTACHMENTS