CC/HR/003

Kind Attn:       HR Department

Project:         2B + G + 14 + Lower Roof Hotel Building

Plot No.:        373-1297 at Barsha, Dubai

Subject:       Issue of non-availability of Labour

Dear HR,

With ref. to above, the Labour who has worked at Citymax site yesterday dt.13.07.16 till 11 PM are supposed to be coming to work at site today by 3:00PM.

But the labours are not available from the camp.

So, kindly take the immediate required actions so that the work at Citymax site will be continued as usual without any delay for level 3 slab.

Regards,

For xxx Contracting L.L.C