Site icon The Engineers Blog

Issue of Electrical drawing for DEWA submission

Substation room

Substation room

Date:               xxx

Ref:                  xxx

Kind Attn         :Mr. xxx

Project:            2B + G + 14+ Lower Roof Hotel Building on Plot No. xxx at Al Barsha 1st, Dubai

Subject             : Regarding the issue of Electrical drawing for DEWA submission and other

                            concern.

Dear Sir,

With reference to the above subject, we would like to inform you the following:

  1. In the kitchen advance drawing the following equipment details which are mention in revise drawing without any product description:
  2. K-65, b. K-66, c. K-67, d. K-68, e. K-69, f. K-70, g. K-71, h. K-72, i. K-73, j. K-74, k. K-75, l. K-76, m. K-77, n. K-78 (Continous follow-up our ref # CC/AP/363/17 dtd. 03.04.17 and Ref.# 4024/CEMC/2017 dtd. 02.04.17)

So, item# 1 needs to be clear by kitchen subcontractor through you and item # 2 client’s ID needs to be provided with the details and the contractor is intimating for the work underhold and delaying the submission of the drawing to DEWA as well as other consequences.

Thank you.

Regards,

For xxx Contracting L.L.C.

xxx

Project Manager

Exit mobile version