Date: xxx
Ref. xxx
To : M/s xxx Trading Company
Project : 2B + G + 14 + Lower Roof Hotels Building, Plot No. xxx at Al Barsha 1st, Dubai
Sub : Regarding fix the pipe from pump room to roof and to establish the pool work.
Dear Mr. Rahul,
With reference to above we would like to inform you that, you did not mobilise the material to start the pool work and water testing over before last 2 days and we need your return confirmation for water testing.
Meantime, our roof plasters under hold due to fixing the pipe for heat/cool pump from pump room to upper roof.
We are also informing you that we have at very tight schedule and we need steel work and concreting for pool within 7 days.
So, please do not delay our work, this is for your kind information and to do needful immediately, as we will remove tower crane on 25.1.2018 and it will be serious issue for
Regards,
For xxx Contracting L.L.C
xxx
Project Manager