Regarding submission of the quotation for slab cutting at pool area
Date: xxx
Ref. xxx
To : M/s xxx Trading Company
Project : 2B + G + 14 + Lower Roof Hotels Building, Plot No. xxx at Al Barsha 1st, Dubai
Subject : Regarding submission of the quotation for slab cutting at pool area which is required by you as per your drawing reference after casting the approval of slab and miscoordination from your end.
Sl. NO | Description | Quantity | Rate | Amount |
1. | Core cutting with saw machine cutting or core cutting/ wire | 3 nos | 1,350 | 4,050 |
2. | Removing debris from the floor the ground to the DM site. | LS | 350 | 350 |
3 | Providing the support below at all three location as required for supporting during the core cutting 1m away from the cutting edge. | 3 nos | 200 | 600 |
4. | Erection of the scaffolding platform which is required for carbon fiber strengthening. | 3 nos | 350 | 1,050 |
5. | The carbon fiber strengthening with 5 year warranty from applied supplier. | 21,500 | ||
6 | Main contractors profit for variation work from sub-contractors quotation (21,500×10%) | 2,150 | ||
TOTAL | 29,700 |
So, kindly review and provide your acceptance to proceed to fulfill the requirement requested from your end as well as we will deduct the amount from your running invoice since you did not highlighted such requirement in your shop drawing.
This is for your immediate response and acceptance, since pool area RCC work under hold because of your new requirement or mitigate the same by using your expertise.
Regards,
For xxx Contracting L.L.C
xxx
Project Manager