Contractor’s Letters

Broken Tiles

Our observation on the tile and awaited for your response

Date: xxx Ref:   CC/269/EVT/01 To:                   The Manager, Envirotec General Trading LLC Project:            2B + G + 14+ Lower Roof Hotel Building on Plot No. 373-1297 at Al Barsha 1st, Dubai, and U.A.E Subject:           Our observation on the tile and awaited for your response Dear Sir, With ref. to above, as per our previous communication we […]

Our observation on the tile and awaited for your response Read Post »

Concreting-of-reinforced-concrete-slab-photo-by-the-author-of-the-paper

Regarding technical and chemical details of the admixture

Date: xxx Ref:   CC/269/CP/02 To:                   Al Ghurair Ready Mix Concrete Plant                         AL quoz, Dubai Project:           2B + G + 14+ Lower Roof Hotel Building on Plot No. 373-1297 at Al Barsha 1st, Dubai, U.A.E Subject:          Regarding technical and chemical details of the admixture Dear Sir, With ref. to your letter AGC-R/GEN/157/16 dated 9th October,

Regarding technical and chemical details of the admixture Read Post »

Concreting-of-reinforced-concrete-slab-photo-by-the-author-of-the-paper

To propose the admixture (retarder) to delay the setting time of cement and that will not affect the properties of concrete including durability and strength

Date: xxx Ref:   CC/269/CP/02 To:                   Al Ghurair Ready Mix Concrete Plant                         AL quoz, Dubai Project:           2B + G + 14+ Lower Roof Hotel Building on Plot No. 373-1297 at Al Barsha 1st, Dubai, U.A.E Subject:          To propose the admixture (retarder) to delay the setting time of cement and that will not affect the properties

To propose the admixture (retarder) to delay the setting time of cement and that will not affect the properties of concrete including durability and strength Read Post »

Testing of the anchor

Request for testing of the anchor for the above mentioned project

Date: xxx Ref:   CC/269/lab/01 To:                   Al Hothy-Stranger Laboratory Project:           2B + G + 14+ Lower Roof Hotel Building on Plot No. 373-1297 at Al Barsha 1st, Dubai, U.A.E Subject:          Request for testing of the anchor for the above mentioned project Dear Sir, With ref. to the above, we are submitting here with the anchor material

Request for testing of the anchor for the above mentioned project Read Post »

Dry Mix Concrete

Request to provide confirmation of maximum time allowable to use the Drymix at the site.

Date: xxx Ref:   CC/269/qmix/01 To:                   Q.Mix Kind Attn:        The Manager Project:            2B + G + 14+ Lower Roof Hotel Building on Plot No. 373-1297 at Al Barsha 1st,        Dubai U.A.E Subject:           Request to provide confirmation of maximum time allowable to use the Drymix at the site which is our consultant – “Arkiplan Consulting Architects and

Request to provide confirmation of maximum time allowable to use the Drymix at the site. Read Post »

AAC Block

Regarding excessive wastage at site and requirement of BS code for tolerance

Date: xxx Ref:  CC/AP/269/ACICO/01  To:             M/s. xxx INDUSTRIES .Co  Kind Attn: Mr. Ahmad Ali, Mr. Suresha  Project:     2B + G + 14+ Lower Roof Hotel Building on Plot No. 373­1297 at Al Barsha 1st, Dubai U.A.E  Subject: Regarding excessive wastage at site and requirement of BS code for tolerance Dear Sir, With reference  to  the  above  and  as  intimated  earlier  by  our  purchase  team on dt.15.08.2016,we would like to inform you again that Mr. Iftakar along with QA/QC Team visited the site and we have the  following concerns: We have witnessed that there is an excessive wastage of the blocks (more than 40%) at site.  The  blocks  are  either  broken  and  the  edges  of  most  of  the  blocks  are  damaged  rendering  them  unusable. The consultant is not allowing us to use these blocks. Please note that this is not only hampering our progress at site but also causing us huge financial losses.

Regarding excessive wastage at site and requirement of BS code for tolerance Read Post »

Tower Crane Support

Regarding tower crane horizontal bracing accessories at third floor

Date: xxx CC/269/TC/01 To:                        Al Balqa Trading Kind Attn:           Mr. Mohammed Saeb Project:               2B + G + 14 + Lower Roof Hotel Building Plot No.:              373-1297 at Barsha, Dubai Subject:              Regarding tower crane horizontal bracing accessories at third floor Dear Sir, With ref. to above, we are here by informing you that we are

Regarding tower crane horizontal bracing accessories at third floor Read Post »

Dewatering

Non acceptance of your invoice duration

Date: 07.07.16 CC/SP/31/16 Kind Attn:        M/s Strong Plant Project:            2B + G + 14 + Lower Roof Hotel Building Plot No.:           373-1297 at Barsha, Dubai Subject:           Non acceptance of your invoice duration Dear Sir, With ref. to above from our letters dt.8/06/16 – ref no: CC/SP/28/16, dt.21/04/16 – ref no: CC/AP/MG/08/16, dt.26/04/16 – ref no:

Non acceptance of your invoice duration Read Post »

Re-route your Dewatering Line

Regarding removal of concrete ramp at road

Date: xxx CC/SP/30/16 Kind Attn:             M/s Strong Plant Project:                2B + G + 14 + Lower Roof Hotel Building Plot No.:              373-1297 at Barsha, Dubai Subject:                Regarding removal of concrete ramp at road Dear Sir, With ref. to above we are here by informing you that what action you are taking regarding removal of the

Regarding removal of concrete ramp at road Read Post »