CONTRACT AGREEMENT

CONTRACT AGREEMENT FOR VANITY COUNETR SUBCONTRACT WORKS

n

About Contract Agreement for Vanity Counetr Subcontract Works

nnn

CC /DENOLEX/003/17                                                                                                                             Date: xxx

nnnn

This Agreement is made between

nnnn

M/s. xxx Contracting LLC (here after called first party), P.O. Box No. 31537 Dubai, UAE (Herein after referred to as “the Main Contractor”)

nnnn

And

nnnn

 M/s. xxx POLYMERS LLC (here after called second party), (Herein after referred to as “the Sub-contractor for supply and installation of Vanity Counter”).

nnnn

Project             : 2B+G+14+LOWER HOTEL BUILDING

nnnn

Plot No.           : xxx

nnnn

Location          : xxx, Dubai, U. A. E.

nnnn

Consultant      : xxx Consulting Architect & Engineers

nnnn

Whereas the First Party is desirous to execute supply and installation of Vanity Counter for the projects through the Second Party under the unit rate basis for supply and installation as per the prevailing rules and regulations in the United Arab Emirates as well as finishing as per client approval with Guarantee/Warranty for all respect and requirement of performance. Therefore the two parties here of have agreed as follows:

nnnn

   Article-1

nnnn

1.1 Scope

nnnn
  1. The scope as agreed in nomination ref no AP/269/308 dt. 12th  July,  xxx and the nomination document including Volume -1 condition of the sub contract (June xxx) from page no 1 to 258. with modified terms and condition (The contract terms and condition to be followed, if not matching with the quotation term and condition of quotation). Measurement and shop drawing to be adjusted as per the site measurement.
nnnn
  • Main contractor terms and conditions which are written with this document to be considered part of the contract with LPO reference 1701163 dt. 24th July, 2017, pg 00 and  pg -1/6 to 6/6.
nnnn
  • The measurement must be taken from the site as per Shop drawing requirement  or Shop drawing can be prepared from the Final drawing and measurement must be taken from the site before fabrication.
  • The drawing and submittals to be completed within 15 days upon signing of the LPO.
  • Quantity to be re measurable and final value to be adjusted as per quantity supplied and fixed.
nnnn

1.2 Material approval/ color shade

nnnn
  1. Material specification as per the approval by the client and consultant.
  2. Three samples of the approved said to be prepared for individual record of the sample.
  3. The final handing over to be defect free and to be accepted by the consultant and client for their satisfaction. Final paint color and finishes sample to be provided on sample board with catalogue  and code.
nnnn

Article-2

nnnn

2 Cost/Payment Terms & Condition

nnnn

2.1 Unit price as per contract document and cost of the contract as per quotation AED       

nnnn

       114,736.00( One Hundred Fourteen Thousand and Seven Hundred Thirty Six

nnnn

       Dirhams Only) will be re adjusted as per final quantity. 

nnnn

2.2 Payment shall be directly released by xxx on the basis of work certification by

nnnn

       the Contractor and the Consultant.

nnnn

2.3 Main Contractor shall coordinate with xxx for timely supply and installation.

nnnn

2.4 Delay if any, shall be intimated to xxx in writing.

nnnn

2.5 10% Retention from the progressive invoice and 5% upto DLP will be kept as per the

nnnn

       Main Contractor Terms & Conditions. Delay if any, penalty AED 300.00 (Three

nnnn

       Hundred Only) will be paid by 2nd party.

nnnn

Article-3

nnnn

Quality & Guarantee/Warranty

nnnn

3.1 Inspection to be raised at every stage before fixing and after fixing.

nnnn

   3.2. The surface finishing as per the satisfaction of the client.

nnnn

 3.3. Material must be submitted immediately for material approval by the consultant and only approved material to be used.

nnnn

       3.4 Lifting and shifting the material by sub-contractor only crane will be provided.

n

Key Aspects of Contract Agreement for Vanity Counetr Subcontract Works

nn

Important Considerations

n

  3.5.   Floor and wall protection surrounding during the painting by the application with their own protection material during maintenance or painting

nnnn

       3.7.   Any damage during the fixing the sub-contractor responsibility to keep safe and sound/damaged free.

nnnn

       3.8.   The defect liability period will be 730 days from date of TOC to the Main Contractor.

nnnn

       3.10. QA /QC policy, procedure and document to be provided.

nnnn

       3.11. Project organization and their contact number communication protocol to be provided.

nnnn

Article-4

nnnn

Schedule

nnnn

      4.1 Main contractor schedule to be followed and sub-contractor must provide their own

nnnn

            schedule within the milestone provided by the main contractor.

nnnn

Article-5

nnnn

Health Safety and House keeping

nnnn

5.1 Health card and visa copy must be submitted to the safety officer.

nnnn

5.2 Health and safety regulation to be followed. Any Individual found to be violating

nnnn

       will be fined AED100 with 1st notice.

nnnn

Article-6

nnnn

Material stacking/scaffolding

nnnn

     6.1 The material to be stored at one of the location at working floor only. The delivered  

nnnn

        materials should not stake at ground level.

nnnn

6.2. Door finishes to be protected during transportation /loading /offloading as well as during fixing.

nnnn

    6.3 Any snag list issued by client/consultant or contractor to be rectified up to their satisfaction and any minor scratch to be eliminated during the handing over.

nnnn

Article-7

nnnn

Termination

nnnn

7.1 The main contractor have right to terminate the contract if, the second party/parties will not perform as per contract or fail to deliver the quality of the deliverable with the notice of termination.

nnnn

     7.2 Any dispute will be resolved amicably or will be resolved within jurisdiction Dubai      court of law.

nnnn

     7.3 Measurement will be considered only for the work completed, no payment to be made for any incomplete work.

nnnn

Article-8

nnnn

8.1 If sub-contractor fail to deliver as per agreed schedule maximum penalty 10% of 2nd   

nnnn

       party contract  value as estimated or final invoice value.

nnnn

Article-9

nnnn

9.1 The following attached document will be considered the part of the document  

nnnn

       attached herewith.  

nnnn

       9.2 Main Contractors term and condition page no 00 and 1/6 to 6/6  including all 

nnnn

             document from Volume no -1 Condition of the sub-contractor form the Main

nnnn

             Contract Document of the Contractor.

nnnn

Agreed by

nnnn

For M/s xxx Contracting LLC,                                   For M/s xxx Polymers  LLC

nnnn

(First party)                                                                         (Second party)

nnnn

xxx                                                        

nnnn

Project Manager                                                                   Authorized Signatory

nnn

Related: Guidance for Reviewing Variation Orders in Construction Projects., Reviewing Variation Orders in Construction Contracts., Essential Guidelines for Project Stakeholder Management.

n

                                                                    

n { “@context”: “https://schema.org”, “@type”: “Article”, “headline”: “Contract Agreement for Vanity Counetr Subcontract Works – CONTRACT AGREEMENT FOR VANITY COUNETR SUBCONTRACT WORKS”, “description”: “CONTRACT AGREEMENT FOR VANITY COUNETR SUBCONTRACT WORKS: Whereas the First Party is desirous to execute supply and installation of Vanity Counter for the p”, “author”: { “@type”: “Person”, “name”: “Md Abu Zaed Khan” }, “datePublished”: “2022-01-27T13:02:29+04:00”, “dateModified”: “2026-06-17T08:38:36+04:00”, “url”: “https://engineersblog.net/contract-agreement-for-vanity-counetr-subcontract-works/” } { “@context”: “https://schema.org”, “@type”: “BreadcrumbList”, “itemListElement”: [ { “@type”: “ListItem”, “position”: 1, “name”: “Home”, “item”: “https://engineersblog.net/” }, { “@type”: “ListItem”, “position”: 2, “name”: “Contractor’s Letters”, “item”: “https://engineersblog.net/contractors-letters/” }, { “@type”: “ListItem”, “position”: 3, “name”: “Contract Agreement for Vanity Counetr Subcontract Works – CONTRACT AGREEMENT FOR VANITY COUNETR SUBCONTRACT WORKS”, “item”: “https://engineersblog.net/contract-agreement-for-vanity-counetr-subcontract-works/” } ] }

Leave a Comment

Your email address will not be published. Required fields are marked *

Scroll to Top