METHOD STATEMENT FOR INSTALLATION,TESTING & COMMISSIONING OF EXTERNAL FIRE HYDRANT

METHOD STATEMENT FOR INSTALLATION,TESTING & COMMISSIONING OF EXTERNAL FIRE HYDRANT

CONTENTS

  1. 1.0 PURPOSE
  2. 2.0 SCOPE
  3. 3.0 REFERENCES
  4. 4.0 DEFINITIONS
  5. 5.0 RESPONSIBILITIES
  6. 6.0 EQUIPMENTS
  7. 7.0 PROCEDURE
  8. 8.0 ATTACHMENTS

 

 

1.0 PURPOSE

  • This method statement is applicable for the Installation, Testing & Commissioning of External Fire Hydrant for the project as mentioned in the Specifications & Approved Shop Drawings.

2.0 SCOPE

  • This method Statement shall cover the Supply, Installation, Testing & Commissioning of External Fire Hydrant in line with project requirements as indicated in the Approved Shop Drawings, specifications & manufacturer’s instructions.

3.0 REFERENCE

      3.1  Latest Approved shop drawings intended for Fire Fighting System

            3.2  Specifications

  • Project Quality Plan
    • Project HSE Plan
    • Material Approval
    • Approved Method Statement for Installation & Testing for Fire Fighting System & Accessories                                                

4.0 DEFINITIONS

  • PQP                             : Project Quality Plan
  • PSP                              : Project Safety Plan
  • QCP                             : Quality Control Procedure
  • HSE                             : Health, Safety and Environment
  • MS                               : Method Statement
  • ITP                               : Inspection Test Plan
  • QA/QC                         : Quality Assurance / Quality Control Engineer.
  • WIR                             : Inspection and Test Request
  • MIR                             : Material Inspection Request
  • UPVC Class E              : Ultra polyvinyl chloride
  • UPVC                          : Ultra polyvinyl chloride
  • HDPE                           : High density polyethylene
  • PEX PIPE                     : Cross-linked Polyethylene
  • G.I. Pipe                       : Galvanized Iron Pipe

5.0 RESPONSIBILITIES:

            5.1 Project Manager

5.2 Construction Manager

5.3 Site Engineer

5.4 QA/QC Engineer (MEP):

5.6 Safety Officer

            5.7 Store Keeper (SK)

6.0  EQUIPMENTS

Following tools shall be arranged before starting the job.

 

7.0   PROCEDURE

 

Ø  Work Sequence/Procedure

  • General Requirements
  •  External Fire Hydrant to be inspected upon receipt & approved by the engineer prior in proceeding with the installation through MIR. Any discrepancies, damages etc., should be reported to the supplier for rectification or replacement & to be removed from site immediately.

            7.2        Delivery & Storage

            7.2.1     Material Transport/ Delivery

7.3        Storage

            7.3.1  Storage on Site Store

            7.4 Sequence of Installation for the External Fire Hydrant

7.4.1 Safety

7.4.2 Pre- Installation Procedure

7.4.3.2.2 Installation Procedure of Butterfly Valves:

7.4.4. Testing & Commissioning Procedures

7.4.4.1 Visual Inspection & Testing Procedure

8.0.  ATTACHMENTS

8.1.            Inspection & Test Plan                                   

8.2.            Installation Check Sheet                                          

  • Testing & Commissioning Check Sheet                  

Risk Assessment 