Delivery Program Update for 001 & 004

Ref                                         : XXX/1437/SUN-030 Date                                      : 15th April XXX To                                           : XXX ENGINEERING AND CONTRACTING Attention                            : Mr. xxx Project                                 : XXX STAFF ACCOMADATION Subject                                 : Delivery Program Update for 001 & 004                               Dear Mr. xxx, We had received a program for the delivery of pods until 16th of April. As mentioned to you earlier we are […]

Interrupting xxx Works 

Ref                                         : XXX/1437/SUN-029 Date                                      : 14th April XXX To                                           : XXX ENGINEERING AND CONTRACTING Attention                            : Mr. xxx Project                                 : XXX STAFF ACCOMADATION Subject                                 : Interrupting XXX Works                    Dear Mr. xxx, We are facing serious issues at site in offloading the pods on time. It’s been agreed in record that xxx Engineering will provide cranes as first priority […]

Missing Unipods Tile Adhesive from site

Ref                                         : XXX/1437/SUN-028 Date                                      : 7th April XXX To                                           : XXX ENGINEERING AND CONTRACTING Attention                            : Mr. xxx Project                                 : XXX STAFF ACCOMADATION Subject                                 : Missing Unipods Tile Adhesive from site Dear Mr. xxx, We want your immediate and serious attention on the xxx Materials missing from site. We have Tiles, Adhesive and grouts in every pod we […]

Leveling the pods

Ref                                         : XXX/1437/SUN-027 Date                                      : 7th April XXX To                                           : XXX ENGINEERING AND CONTRACTING Attention                            : Mr. xxx Project                                 : XXX STAFF ACCOMADATION Subject                                 : Leveling the pods Dear Mr. xxx, During our coordination meeting on 31st March xxx we discussed about the level on the floors and under your strict instruction to site team we are placing […]

Issues in Delivery and leveling of the pods

Ref                                         : XXX/1437/SUN-026 Date                                      : 30th March XXX To                                           : XXX ENGINEERING AND CONTRACTING Attention                            : Mr. XXX Project                                 : XXX STAFF ACCOMADATION Subject                                 : Issues in Delivery and leveling of the pods Dear Mr. xxx, There are 2 major issues we want your immediate attention and instructions. The above point is critical as this will reflect in […]

Pods delivered Schedule

Ref                                         : XXX/1437/SUN-024 Date                                      : 17th March XXX To                                           : XXX ENGINEERING AND CONTRACTING Attention                            : Mr. XXX Project                                 : XXX STAFF ACCOMADATION Subject                                 : Request for Wiring Colour Code for Plot 005 & 006 Pages                                    : Pods delivered Schedule Dear Mr. Jamal, As requested in the coordination meeting, Please find below the forecast of the pods delivered […]

Request for Wiring Colour Code for Plot 005 & 006

Ref                                         : XXX/1437/SUN-024 Date                                      : 06th March XXXX To                                           : XXX ENGINEERING AND CONTRACTING Attention                            : Mr. xxx Project                                 : XXX STAFF ACCOMADATION Subject                                 : Request for Wiring Colour Code for Plot 005 & 006 Dear Mr. xxx, Please provide us with the required wiring colour code for the pods in the building 005 & 006 Double and […]

Reminder letter request for wiring Colour Code for Plot 005 & 006

Ref                                         : XXX/1437/SUN-024-R1 Date                                      : 15th April XXXX To                                           : XXX ENGINEERING AND CONTRACTING Attention                            : Mr. xxx Project                                 : XXX STAFF ACCOMADATION Subject                                 : Reminder letter request for wiring Colour Code for Plot 005 & 006 Dear Mr. Jamal, We have requested on 6th of March regarding the colour code for the pods in the building of […]

Schedule of Payment (%)

Ref                                         : XXX/1437/SUN-023 Date                                      : 06th March XXX To                                           : XXX ENGINEERING AND CONTRACTING Attention                            : Mr. XXX Project                                 : XXX STAFF ACCOMADATION Subject                                 : Schedule of Payment (%) Dear Mr. xxx, In reference to your letter regarding the schedule of payment (Percentage), we studied your proposal and respond as follows, During the coming 4 weeks we will […]

Sanitary ware and accessories

Ref                                         : XXX/1437/SUN-022 Date                                      : 06th March XXXX To                                           : XXX ENGINEERING AND CONTRACTING Attention                            : Mr. xxx Project                                 : XXX STAFF ACCOMADATION Subject                                 : Sanitary ware and accessories    Dear Mr. xxx, As requested in your letter Ref No: SUN-14-244-JRA-xxx 079, please find along with this letter the price breakdown of the sanitary and Accessories. This is […]