Project status update for discussion

Date:               xxx Ref:                  xxx Kind Attn         :Mr. xxx Project:            2B + G + 14+ Lower Roof Hotel Building on Plot No. xxx at Al Barsha 1st, Dubai Subject:            Status up date for discussion help on 29.03.17 at site. Dear Sir, With reference to the above, we would like to inform you that on 29th […]

Project status update for discussion Read Post »

Tower Crane

Your Instruction for Tower Crane and our reply

Date:               xxx Ref:                  xxx Kind Attn         :Mr. xxx Project:            2B + G + 14+ Lower Roof Hotel Building on Plot No. xxx at Al Barsha 1st, Dubai Subject:             Your Instruction for Tower Crane and our reply Dear Sir, With reference to above, as we extended the tower crane by adding 3 members with minor

Your Instruction for Tower Crane and our reply Read Post »

Slow Progress

Slow progress of work- External Plaster

Date:               xxx Ref:                  xxx Kind Attn         :Mr. xxx Project:            2B + G + 14+ Lower Roof Hotel Building on Plot No. xxx at Al Barsha 1st, Dubai Subject:             Reply to your letter Ref: xxx reegaring slow progress of work- External Plaster Dear Sir, With reference to the above, we would like to inform you

Slow progress of work- External Plaster Read Post »

Chiller

Chiller delivery and the payment from the supplier

Date:               xxx Ref:                  xxx Kind Attn         :Mr. xxx Project:            2B + G + 14+ Lower Roof Hotel Building on Plot No. xxx at Al Barsha 1st, Dubai Subject:             Intimation of the Chiller delivery and the payment from the supplier and release the payment. Dear Sir, With reference to the above, the expected delivery of

Chiller delivery and the payment from the supplier Read Post »

Painting works

Issue regarding third resubmission of internal paint sample boards

Date:               xxx Ref:                  xxx Kind Attn         :Mr. xxx Project:            2B + G + 14+ Lower Roof Hotel Building on Plot No. xxx at Al Barsha 1st, Dubai Subject         :  Issue regarding third resubmission of internal paint sample boards and final submission with request to forward the same to ID. Dear Sir, With reference to the

Issue regarding third resubmission of internal paint sample boards Read Post »

Engineering Submittals

No objection to retain the originally approved beam enforcement and size

Date:               xxx Ref:                  xxx Kind Attn         :Mr. xxx Project:            2B + G + 14+ Lower Roof Hotel Building on Plot No. xxx at Al Barsha 1st, Dubai Subject         : Our no objection to retain the originally approved beam enforcement and   size Dear Sir, With reference to the above, we are hereby confirming that we have

No objection to retain the originally approved beam enforcement and size Read Post »

dry wall partition works

Revision in the wall design by increasing the acoustic value from 45 dB to 55 dB,                           Replace wall P07 to P02

Date:               xxx Ref:                  xxx Kind Attn         :Mr. xxx Project:            2B + G + 14+ Lower Roof Hotel Building on Plot No. xxx at Al Barsha 1st, Dubai Dear Sir, With reference to the above, the toilet wall between Unit No.1 & 2 as well as Unit No. 3 & 4 in our approved drawing for

Revision in the wall design by increasing the acoustic value from 45 dB to 55 dB,                           Replace wall P07 to P02 Read Post »

awaiting-response

Intimation to the new Document controller authorization to transmit documents.

Date:               xxx Ref:                  xxx Kind Attn         :Mr. xxx Project:            2B + G + 14+ Lower Roof Hotel Building on Plot No. xxx at Al Barsha 1st, Dubai Subject         :    Intimation to the new Document controller authorization to transmit documents. Dear Sir, With reference to the above, we are hereby informing Engr. xxx Indulal has been

Intimation to the new Document controller authorization to transmit documents. Read Post »

Engineering Submittals

Submission of MEP Variation Summary

Date:               xxx Ref:                  xxx Kind Attn         :Mr. xxx Project:            2B + G + 14+ Lower Roof Hotel Building on Plot No. xxx at Al Barsha 1st, Dubai Subject             Submission of MEP Variation Summary Dear Sir, With reference to the above we are hereby submitting the MEP Variation as per the changes in Drawings issued from

Submission of MEP Variation Summary Read Post »

Vanity Counter

Reply to your letter regarding Vanity counters

Date:               xxx Ref:                  xxx Kind Attn         :Mr. xxx Project:            2B + G + 14+ Lower Roof Hotel Building on Plot No. xxx at Al Barsha 1st, Dubai Subject        Reply to your letter Ref : AP/269/CC/288 dated 26.03.2017 regarding Vanity counters Dear Sir, With reference to the above and your letter Ref : CC/AP/348/17 we clarify

Reply to your letter regarding Vanity counters Read Post »