Request to provide clearance for Nomination of various subcontractors

Date:               xxx Ref:                  xxx Kind Attn         :Mr. xxx Project:            2B + G + 14+ Lower Roof Hotel Building on Plot No. xxx at Al Barsha 1st, Dubai Subject      :    Request to provide clearance for Nomination of various subcontractors Dear Sir With reference to the above, we request you to kindly provide us the clearance for […]

Request to provide clearance for Nomination of various subcontractors Read Post »

False ceiling work

Regarding Nomination –Public area Fit out works

Date:               xxx Ref:                  xxx Kind Attn         :Mr. xxx Project:            2B + G + 14+ Lower Roof Hotel Building on Plot No. xxx at Al Barsha 1st, Dubai Subject    : Regarding Nomination –Public area Fit out works (M/s xxx Group and                     M/s xxx Interior’s) Dear Sir, With reference to the above and your Letter Ref:

Regarding Nomination –Public area Fit out works Read Post »

MONTHLY PROGRESS REPORT

Monthly Report Template

Table of Contents PROJECT DESCRIPTION.. 2 1.1 PROJECT DETAILS. 2 1.2 PROJECT COMPONENT. 2 1.3 PROJECT DATA. 2 1.4 CONSTRUCTION PROGRAMME BRIEF. 3 PROJECT ORGANOGRAM.. 4 PROJECT STATUS. 5 3.1 KEY PARAMETERS. 5 3.2 DASH BOARD REPORT. 6 3.3 PROGRESS SUMMARY. 7 3.4 CONTRACT DURATION DETAILS IN DAYS: 8 3.5 CONTRACT DURATION DETAILS IN PERCENTAGES:

Monthly Report Template Read Post »

advance payment

Request to client to pay directly to the supplier for long lead item

Date:               xxx Ref:                  xxx Kind Attn         :Mr. xxx Project:            2B + G + 14+ Lower Roof Hotel Building on Plot No. xxx at Al Barsha 1st, Dubai Subject             :  Request to client to pay directly to the supplier for long lead item or major procurement items. Dear Sir, With regards to the subject above, as

Request to client to pay directly to the supplier for long lead item Read Post »

threshold

The type of the threshold sample  between corridors and rooms

Date:               xxx Ref:                  xxx Kind Attn         :Mr. xxx Project:            2B + G + 14+ Lower Roof Hotel Building on Plot No. xxx at Al Barsha 1st, Dubai Subject            :  Regarding the type of the threshold sample  between corridors and rooms for all areas Dear Sir, With regards to the subject above, and our sample submittal

The type of the threshold sample  between corridors and rooms Read Post »

Engineering Submittals

To claim variation in Invoice no 13

Date:               xxx Ref:                  xxx Kind Attn         :Mr. xxx Project:            2B + G + 14+ Lower Roof Hotel Building on Plot No. xxx at Al Barsha 1st, Dubai Subject            : To claim variation in Invoice no 13, carried out for client Due to xxx  work. Dear Sir, With reference to above, we would like to intimate

To claim variation in Invoice no 13 Read Post »

CCTV Camera

To provide approved quotation by xxx and provided by M/s xxx Emirates  and Networking LLC

Date:               xxx Ref:                  xxx Kind Attn         :Mr. xxx Project:            2B + G + 14+ Lower Roof Hotel Building on Plot No. xxx at Al Barsha 1st, Dubai Subject         :   To provide approved quotation by xxx and provided by M/s xxx Emirates  and Networking LLC Dear Sir, With reference to above, we received through  the mail

To provide approved quotation by xxx and provided by M/s xxx Emirates  and Networking LLC Read Post »

Manhole-Excavation

Regarding Execution outside RMU room to cut the steel beam

Date:               xxx Ref:                  xxx Kind Attn         :Mr. xxx Project:            2B + G + 14+ Lower Roof Hotel Building on Plot No. xxx at Al Barsha 1st, Dubai Subject              :   Regarding Execution outside RMU room to cut the steel beam and encounter the huge concrete. Dear sir, With reference to the above mentioned subject,  as per

Regarding Execution outside RMU room to cut the steel beam Read Post »

Engineering Submittals

MEP Ducting work under hold due to AC grill issue

Date:               xxx Ref:                  xxx Kind Attn         :Mr. xxx Project:            2B + G + 14+ Lower Roof Hotel Building on Plot No. xxx at Al Barsha 1st, Dubai Subject              :   Regarding MEP/ Ducting work under hold due to AC grill issue. Dear sir, With reference to the above mentioned subject we would like to inform you

MEP Ducting work under hold due to AC grill issue Read Post »

Slow Progress

Reply – Reason of slow progress for External block work

Date:               xxx Ref:                  xxx Kind Attn         :Mr. xxx Project:            2B + G + 14+ Lower Roof Hotel Building on Plot No. xxx at Al Barsha 1st, Dubai Subject      :  Reply to your Letter ref. AP/269/CC/298 dtd.03/04/2017, Reason of slow progress for External block work Dear sir, With reference to above, regarding external block work and