Bathtub overflow fittings rejection by consultant

Date:               xxx Ref:                  xxx Kind Attn         :Mr. xxx Project:            2B + G + 14+ Lower Roof Hotel Building on Plot No. xxx at Al Barsha 1st, Dubai    Subject        : Regarding Bathtub overflow fittings deliverd by STstyle LLC on xxx and inspection rejection by consultant. Dear Sir, With reference to above, the Bathtub fittings material delivery by the client soupier […]

Lighting control issue pending and our concern at site.

Date:               xxx Ref:                  xxx Kind Attn         :Mr. xxx Project:            2B + G + 14+ Lower Roof Hotel Building on Plot No. xxx at Al Barsha 1st, Dubai    Subject       : Regarding lighting control issue pending and our concern at site. Dear Sir, With reference to above, we would like to put your kind notice that we submitted variation work quotation […]

Kitchen sub contractor visit at site and work carried out

Date:               xxx Ref:                  xxx Kind Attn         :Mr. xxx Project:            2B + G + 14+ Lower Roof Hotel Building on Plot No. xxx at Al Barsha 1st, Dubai Subject      : Regarding Kicthen sub contractor visit at site and work carried out as per advance copy issued from your office. Dear Sir, We are hereby informing you that Emirated Kitchen nominated sub […]

DEWA Comments Regarding Transformer Rating.

Date:               xxx Ref:                  xxx Kind Attn         :Mr. xxx Project:            2B + G + 14+ Lower Roof Hotel Building on Plot No. xxx at Al Barsha 1st, Dubai Subject:               DEWA Comments Regarding Transformer Rating. Dear Sir, With reference to the above subject, our meeting with your MEP team and kindly note the following. We received comment from DEWA on dtd: […]

Commencement of painting work prior to issue LPO

Date:               xxx Ref:                  xxx Kind Attn         :Mr. xxx Project:            2B + G + 14+ Lower Roof Hotel Building on Plot No. xxx at Al Barsha 1st, Dubai Subject:             Commencement of painting work prior to issue LPO. Dear Sir. With reference to above, we are here by intimating that the nominated painting sub contractor has steered the internal painting work […]

Discrepancy in nomination letter issued

Date:               xxx Ref:                  xxx Kind Attn         :Mr. xxx Project:            2B + G + 14+ Lower Roof Hotel Building on Plot No. xxx at Al Barsha 1st, Dubai Subject     :  Discrepancy in nomination letter issued on 15th August xx xxx and another communication xxx ON 19TH August xxx. Dear Sir, With reference to above, we have two different instructions which created […]

Request to modify the lower roof PT drawing due to heavy beam reinforcement

Date:               xxx Ref:                  xxx Kind Attn         :Mr. xxx Project:            2B + G + 14+ Lower Roof Hotel Building on Plot No. xxx at Al Barsha 1st, Dubai Subject     :  Request to modify the lower roof PT drawing due to heavy beam reinforcement Dear Sir, With reference to above, we have practical problem to fix the anchor outside of the beam […]

Submission of variation order no-18 and request to release the variation work instruction.

Date:               xxx Ref:                  xxx Kind Attn         :Mr. xxx Project:            2B + G + 14+ Lower Roof Hotel Building on Plot No. xxx at Al Barsha 1st, Dubai Subject        :  Submission of variation order no-18 and request to release the variation work instruction. Dear Sir, With reference to above, we are here by submitting the variation work which is required for […]

Mediahub GI boxes and Bathtub fittings still not supplied by employer.

Date:               xxx Ref:                  xxx Kind Attn         :Mr. xxx Project:            2B + G + 14+ Lower Roof Hotel Building on Plot No. xxx at Al Barsha 1st, Dubai Subject        :  Reminder Regarding Mediahub GI boxes and Bathtub fittings still not supplied by employer. Dear Sir, With reference to above, we would like to inform you that we donot have GI boxes […]

Hollow Metal Door sub-contractor payment terms issue

Date:               xxx Ref:                  xxx Kind Attn         :Mr. xxx Project:            2B + G + 14+ Lower Roof Hotel Building on Plot No. xxx at Al Barsha 1st, Dubai Subject        : Regarding Hollow Metal Door sub-contractor payment terms issue. Dear All, With reference to above mentioned subject, we are attaching a mail from xxx on14thxxx.kindly review/decide their payment terms which is self-explanatory […]