Undertaking for law height form work for slab above ettic slab (0.7m height) and pool deck.

Concreting-of-reinforced-concrete-slab-photo-by-the-author-of-the-paper
Concreting-of-reinforced-concrete-slab-photo-by-the-author-of-the-paper

Date: xxx

Ref no: CC/DT/DM/13

To,

Dubai Municipality

Building Control section

Dubai, UAE

Project      : 2B + G + 14+ Lower Roof Hotels Building on Plot No. 373-1297 at Barsha, Dubai

Sub               : Undertaking for law height form work for slab above ettic slab (0.7m   height) and pool deck.

Dear Sir,

With reference to the above, we are hereby undertaking that our formwork for 0.7m height slab above ettic slab and the equipment room (1.8m height) is stable/safe and braced properly and followed the approved drawing.

The area of the low height slab between grid no 5 to 8/A-G at roof.

Regards,

For xxx Contracting L.L.C

xxx

Project Manager

By Md Abu Zaed Khan

Hello, this is Engr. Zaed Khan Planning Engineer, Associate member of Society of Engineers UAE. Expert in construction project planning, FIDIC red book, computation of extension of time claim, Contract agreement and contractual letters.