Date: xxx
Ref no: CC/HC/009
To : M/s xxx Center
Attn : Mr. xxx
Project : 2B + G + 14+ Lower Roof Hotels Building on Plot No. 373-1297 at Barsha, Dubai
Subject : To provide clearance for the False ceiling work in guest room passage in typical floor. (Mock up room)
Dear Sir,
With reference to the above, we are here by requesting you we need your clearance that your sliding door work has been complete100% in mock up room unit no -05 and we want to start our false ceiling work.
So, we are hereby intimates you to provide written confirmation as our successor activity will be executed after clearance.
Regards
For xxx Contracting L.L.C
xxx
Project manager