Date | : | xxx |
Ref No. | : | CC/DESTEC/021 |
To | : | M/s. xxx GROUP, PO Box 47395, Sharjah UAE |
Project | : | 2B+G+14+Lower Roof Hotels Building on Plot No. 373-1297 at Al Barsha |
Subject | : | To fix the floor tile in first floor corridor outside of All Day Dining |
Dear Mr.xxx,
With reference to the above, we have issued variation work to fix the tile/ continue from All Day Dining area to consider/passage.
So, up to how you didn’t execute the scope and variation instruction issued to you by client long before.
Kindly do needful as soon as possible and acknowledge the same.
Best Regards
For xxx Contracting LLC
xxx
Project Manager