Substation room

Submission status of the substation.

Date:               xxx

Ref:                  xxx

Kind Attn         :Mr. xxx

Project:            2B + G + 14+ Lower Roof Hotel Building on Plot No. xxx at Al Barsha 1st, Dubai

Subject          : Submission status of the substation.

Dear Sir,

With the reference to the above, the LV room panel supplier intimated that they must test the panel prior to test from their factory.so they would like to know that the consultant will accept their test report carried out in the factory by them or the consultant remain present during the performing of the test at panels.

This is for your kind information and replay awaited. In case of your presence we will inform you the time and date a day before if you want to be present during the testing.

Regards,

For xxx Contracting L.L.C.

xxx

Project Manager

Leave a Comment

Your email address will not be published. Required fields are marked *

Scroll to Top