Date: xxx
Ref: xxx
Kind Attn :Mr. xxx
Project: 2B + G + 14+ Lower Roof Hotel Building on Plot No. xxx at Al Barsha 1st, Dubai
Subject : Status of pending activities
Dear Sir,
With reference to the above, we are hereby submitting the location wise status update and the impact of of the predecessor activity on the successor activities, in a chart format.
Kindly note the following in this regard:
- Work underhold at locations mentioned for usscesor activities until Employer resolves the issue.
- The Column of the prededcessor activity states the requirement for its completion, which is either supply, nomination, approval of vartiation of shop drawings.
- Status of successor activity is self explanatory, they activities will remain ubderhold till the requirements the predescessor activittes are met.
So, further to numerous earlier intimations, kindly find the status update for the activities that are pending as we are awaiting the action to be taken from your end for the areas and activities underhold to avoid further delay.
Regards,
For xxx Contracting L.L.C.
xxx
Project Manager