ledge wall

RFI submission for ledge wall and floor trap location

Date:               xxx

Ref:                  xxx

Kind Attn         :Mr. xxx

Project:            2B + G + 14+ Lower Roof Hotel Building on Plot No. xxx at Al Barsha 1st, Dubai

Subject              : RFI submission for ledge wall and floor trape location and issue 

Dear Sir,

With reference to above subject, we would like to request you to review our concern as described below and advise accordingly

  1. Our Floor trape position in typical floor was kept as per ledge wall approved contract drawing with the width that is 200 mm and sleaves kept as per darinage drawing approved.
  •  The ID drawing issued by the clientl edge wall width increased and it is 300 mm instead of 200 mm.
  • The ledge wall edge shifted closer to floor trape position and we cannot fixed the floor trape and cannot be  modified due to structural constraint and PT tendom position
  • Our RFI CEM/269/RFI/19 dated 17.05.17 raised to review and this issue already highlighted to client ID team at site in last week already to work out in their drawing 

So, this is for your kind information to review and resolved and our ledge wall work in toilet remain suspended till issue not concluded by SME.

Regards,

For xxx Contracting L.L.C.

xxx

Project Manager

Leave a Comment

Your email address will not be published. Required fields are marked *

Scroll to Top