Date: xxx
Ref: xxx
Kind Attn :Mr. xxx
Project :2B + G + 14 + Lower Roof Hotel Building on Plot No. xxx at Al Barsha
1st, Dubai U.A.E.
Subject : Regarding to issue MEP IFC drawings for the revised 14th floor layout
Dear Sir,
With reference to the above, as per your letter ref no:AP/C269/CC/242 dt.15.02.17, we would like to inform you that we need MEP IFC drawings for the 14th floor based on the revised floor plan for 14th floor A-109 received.
Once the IFC drawings are issued, we shall prepare and submit the MEP shop drawings for approval.
So request you to please release the MEP IFC drawings for the 14th floor at the earliest.
Regards,
For xxx Contracting L.L.C.
xxx
Project Manager