Reply – Notification of Delay
Ref: xxx
Date: February 18, xxx
To,
xxx ARCHITECTURAL & ENGINEERING CONSULTANCY
Office No. xxx, Sobha Ivory 2, Business Bay
P.O. Box xxx, Dubai, UAE
Project: Residential Villa (G+1) & Pump Room Block, On Plot No. 6xxx at Al Barari – Dubai, UAE for Mr. xxx
Subject: Reply – Notification of Delay
Dear Sir,
This is further to your letter ref. AAEC/DB/3244/22/AS dated 15th February xxx, most of the items has submitted and under engineering approval process. The balance three items will be submitted within next week. Following are MCM response.
SL | ATRIUM COMMENTS | MCM RESPONSE |
1 | Submission of MDB, DB and SMDB: Negative 6 days. | Supplier and manufacture prequalification under review, will be submitted by 18th February xxx. |
2 | Submission of water transfer pump sets: Negative 75 days | Already approved from PDP |
3 | Submission of sump pump: Negative 73 days | Already approved from PDP |
4 | Submission of booster pump: Negative 69 days | Already approved from PDP |
5 | Submission of circulation pump: Negative 69 days | Already approved from PDP |
6 | Submission of GRP panel water tank: Negative 49 days | Submission is under review, will be submitted by 20-Feb-xx |
7 | Submission of FCU: Negative 49 days | Submitted on 17-Feb-xx. |
8 | Submission of variable refrigerant unit: Negative 56 days | Submitted on 17-Feb-xx |
9 | Submission of exhaust fan: Negative 49 days | Under review, will be submitted by 22-Feb-xx. |
We would like to highlight that, despite of multiple obstruction from authority, neighbor for the swimming dewatering work, we have recovered the delay and now it’s almost 0 float for construction activity. The delay in engineering submission and approval will also be recovered soon.
Yours Sincerely,
MCM LLC