Ref : XXX/1437/XXX-050
Date : 03th July XXX
To : XXX ENGINEERING AND CONTRACTING
Attention : Mr. xxx
Project : XXX STAFF ACCOMADATION
Subject : Reply for Letter Unipods 186 (Delay of Works)
Dear Mr. xxx,
Please be informed that xxx haven’t got any official MEP clearance from xxx Engineering to complete our false ceiling works in the pods. The materials and work force is already available at site. From the meeting yesterday with the client and consultant representatives it was clear that xxx clearance above the ceiling for the Plot OAS 006, Block 4 is on 28th of January. So there is no delay from xxx site so far in the work progress.
Below mentioned are the dates given to Unipods as clearance confirmation from Al Hani.
PLOT 006 Block 4 28th January xxxx
Block 3 28th January xxxx
Block 6 29th January xxxx
Block 5 31st January xxxx
Block 2 03rd February xxxx
Block 1 07th February xxxx
Any false ceiling removed from our pods after the works are finished, xxx cannot take the responsibility for the damages and cleaning.
Hope you understand and will do the needful.
Regards,
xxx
Projects Manager