Dewatering

Regarding Well Closing Method Statement Including Sequence

Date: xxx

CC/AP/MG/08/16

Kind Attn:       M/s Strong Plant

Project:            2B + G + 14 + Lower Roof Hotel Building

Plot No.:           373-1297 at Barsha, Dubai

Subject:          Regarding Well Closing Method Statement Including Sequence

Dear Sir,

With reference to the above mentioned subject, we already conform with our consultant to close the Dewatering System. Kindly provide the following:

  1. The sequence of the well closing from upper area to lower area, well to well.
  • Seal the well point pipe as per your approved method statement.
  • The consideration of the deep area, practical difficulties in tank & pump room area.

So, kindly visit the site and discuss to us. Also, bring the documents immediately.

Regards,

For xxx Contracting L.L.C

xxx

General Manager                      

Leave a Comment

Your email address will not be published. Required fields are marked *