Date: xxx
Ref: xxx
Kind Attn :Mr. xxx
Project: 2B + G + 14+ Lower Roof Hotel Building on Plot No. xxx at Al Barsha 1st, Dubai
Subject : Regarding the request to issue the revised RCP drawing
Dear Sir,
With reference to above subject and the revision in the RCP for AC grill position and the discussion on the drawings for concept finalization.
Kindly issue the revise RCP drawing by incorporating the following and discussion held with client’s ID team:
- The lift area lobby ceiling concept with the conjunction of the corridor because the transition point location and detailed to be coordinated, you also revise the drawing by eliminating gypsum penall with plain gypsum board.
- The transition line and corridor, the sectional detail beacause the penal direction being change in your drawing to be finally decided
- The bulk head direction near OTS and edge of the ceiling limit infront of the lift area to be concluded by considering all factor with floor line and floor concept
- The AC grill will be fix as per concept approve with down throw as per sketch approved will be incorporated in final coordination drawing.
- The material for plain ceiling will be 12.5 mm gypsum board and the penall will be painted one as shown in ID-1524-35-005 drawings as well as P11 ID-paint code (paint table penal sample available at site)
So, kindly provide one final concept drawing for false ceiling and we will submit our MEP Coordination drawing for approva first and the detailed ceiling drawing with coordination of MEP services will be followed/ submitted accordingly.
Regards,
For xxx Contracting L.L.C.
xxx
Project Manager