Pelmet mockup

Regarding Pelmet Mock up approval in unit no 5 & 6

Date: xxx

Ref: CC/269/CM/84

To                   : M/s. xxx Hotels, Dubai, UAE

Kind Attn.     : Mr. xxx

Project          : 2B + G + 14+ Lower Roof Hotel Building on Plot No. 373-1297 at Al    Barsha 1st, DubaiU.A.E.

     Subject          :   Regarding  Pelmet Mock up approval in unit no 5 & 6

Dear Sir,

With reference to the above subject we are here by requesting as you called me verbally that you are approving the pelmet mock up in unit no 5 & 6 prepared by DESTEC.

Please note that you instructed that the DESTEC  IR  will be signed by you and you do not required gypsum cladding inside.

So kindly confirm the pelmet for DESTEC either in mail or sign their inspection as their previous inspection was rejected on 24/12/17 and they resubmitted.

Regards,

For xxx Contracting L.L.C

xxx

Project Manager

Leave a Comment

Your email address will not be published. Required fields are marked *

Scroll to Top